arallel Operation of Transformers

JULY 17, 2012 24 COMMENTS

Introduction:

§                     For supplying a load in excess of the rating of an existing transformer, two or more transformers may be connected in parallel with the existing transformer. The transformers are connected in parallel when load on one of the transformers is more than its capacity. The reliability is increased with parallel operation than to have single larger unit. The cost associated with maintaining the spares is less when two transformers are connected in parallel.

§                     It is usually economical to install another transformer in parallel instead of replacing the existing transformer by a single larger unit. The cost of a spare unit in the case of two parallel transformers (of equal rating) is also lower than that of a single large transformer. In addition, it is preferable to have a parallel transformer for the reason of reliability. With this at least half the load can be supplied with one transformer out of service.

Condition for Parallel Operation of Transformer:

§                     For parallel connection of transformers, primary windings of the Transformers are connected to source bus-bars and secondary windings are connected to the load bus-bars.

§                     Various conditions that must be fulfilled for the successful parallel operation of transformers:

1.                    Same voltage Ratio & Turns Ratio (both primary and secondary Voltage Rating is same).

2.                   Same Percentage Impedance and X/R ratio.

3.                   Identical Position of Tap changer.

4.                   Same KVA ratings.

5.                   Same Phase angle shift (vector group are same).

6.                   Same Frequency rating.

7.                   Same Polarity.

8.                   Same Phase sequence.

§                     Some of these conditions are convenient and some are mandatory.

§                     The convenient are: Same voltage Ratio & Turns Ratio, Same Percentage Impedance, Same KVA Rating, Same Position of Tap changer.

§                     The mandatory conditions are: Same Phase Angle Shift, Same Polarity, Same Phase Sequence and Same Frequency.

§                     When the convenient conditions are not met paralleled operation is possible but not optimal.

 1.Same voltage Ratio & Turns Ratio (on each tap):

§                      If the transformers connected in parallel have slightly different voltage ratios, then due to the inequality of induced emfs in the secondary windings, a circulating current will flow in the loop formed by the secondarywindings under the no-load condition, which may be much greater than the normal no-load current.

§                     The current will be quite high as the leakage impedance is low. When the secondary windings are loaded, this circulating current will tend to produce unequal loading on the two transformers, and it may not be possible to take the full load from this group of two parallel transformers (one of the transformers may get overloaded).

§                     If two transformers of different voltage ratio are connected in parallel with same primary supply voltage, there will be a difference in secondary voltages.

§                     Now when the secondary of these transformers are connected to same bus, there will be a circulating current between secondary’s and therefore between primaries also. As the internal impedance of transformer is small, a small voltage difference may cause sufficiently high circulating current causing unnecessary extra I2R loss.

§                     The ratings of both primaries and secondary’s should be identical. In other words, the transformers should have the same turn ratio i.e. transformation ratio.

2. Same percentage impedance and X/R ratio:

§                      If two transformers connected in parallel with similar per-unit impedances they will mostly share the load in the ration of their KVA ratings. Here Load is mostly equal because it is possible to have two transformers with equal per-unit impedances but different X/R ratios. In this case the line current will be less than the sum of the transformer currents and the combined capacity will be reduced accordingly.

§                     A difference in the ratio of the reactance value to resistance value of the per unit impedance results in a different phase angle of the currents carried by the two paralleled transformers; one transformer will be working with a higher power factor and the other with a lower power factor than that of the combined output. Hence, the real power will not be proportionally shared by the transformers.

§                     The current shared by two transformers running in parallel should be proportional to their MVA ratings.

§                     The current carried by these transformers are inversely proportional to their internal impedance.

§                     From the above two statements it can be said that impedance of transformers running in parallel are inversely proportional to their MVA ratings. In other words percentage impedance or per unit values of impedance should be identical for all the transformers run in parallel.

§                     When connecting single-phase transformers in three-phase banks, proper impedance matching becomes even more critical. In addition to following the three rules for parallel operation, it is also a good practice to try to match the X/R ratios of the three series impedances to keep the three-phase output voltages balanced.

§                     When single-phase transformers with the same KVA ratings are connected in a Y-∆ Bank, impedance mismatches can cause a significant load unbalance among the transformers

§                     Lets examine following different type of case among Impedance, Ratio and KVA.

§                     If single-phase transformers are connected in a Y-Y bank with an isolated neutral, then the magnetizing impedance should also be equal on an ohmic basis. Otherwise, the transformer having the largest magnetizing impedance will have a highest percentage of exciting voltage, increasing the core losses of that transformer and possibly driving its core into saturation.

           Case 1: Equal Impedance, Ratios and Same kVA:

§                      The standard method of connecting transformers in parallel is to have the same turn ratios, percent impedances, and kVA ratings.

§                      Connecting transformers in parallel with the same parameters results in equal load sharing and no circulating currents in the transformer windings.

§                     Example: Connecting two 2000 kVA, 5.75% impedance transformers in parallel, each with the same turn ratios to a 4000 kVA load.

§                     Loading on the transformers-1 =KVA1=[( KVA1 / %Z) / ((KVA1 / %Z1)+ (KVA2 / %Z2))]X KVAl

§                     kVA1 = 348 / (348 + 348) x 4000 kVA = 2000 kVA.

§                     Loading on the transformers-2 =KVA1=[( KVA2 / %Z) / ((KVA1 / %Z1)+ (KVA2 / %Z2))]X KVAl

§                     kVA2 = 348 / (348 + 348) x 4000 kVA = 2000 kVA

§                     Hence KVA1=KVA2=2000KVA

            Case 2: Equal Impedances, Ratios and Different kVA:

§                      This Parameter is not in common practice for new installations, sometimes two transformers with different kVAs and the same percent impedances are connected to one common bus. In this situation, the current division causes each transformer to carry its rated load. There will be no circulating currents because the voltages (turn ratios) are the same.

§                     Example: Connecting 3000 kVA and 1000 kVA transformers in parallel, each with 5.75% impedance, each with the same turn ratios, connected to a common 4000 kVA load.

§                     Loading on Transformer-1=kVA1 = 522 / (522 + 174) x 4000 = 3000 kVA

§                     Loading on Transformer-1=kVA2 = 174 / (522 + 174) x 4000 = 1000 kVA

§                     From above calculation it is seen that different kVA ratings on transformers connected to one common load, that current division causes each transformer to only be loaded to its kVA rating. The key here is that the percent impedance are the same.

            Case 3: Unequal Impedance but Same Ratios & kVA:

§                      Mostly used this Parameter to enhance plant power capacity by connecting existing transformers in parallel that have the same kVA rating, but with different percent impedances.

§                     This is common when budget constraints limit the purchase of a new transformer with the same parameters.

§                     We need to understand is that the current divides in inverse proportions to the impedances, and larger current flows through the smaller impedance. Thus, the lower percent impedance transformer can be overloaded when subjected to heavy loading while the other higher percent impedance transformer will be lightly loaded.

§                     Example: Two 2000 kVA transformers in parallel, one with 5.75% impedance and the other with 4% impedance, each with the same turn ratios, connected to a common 3500 kVA load.

§                     Loading on Transformer-1=kVA1 = 348 / (348 + 500) x 3500 = 1436 kVA

§                     Loading on Transformer-2=kVA2 = 500 / (348 + 500) x 3500 = 2064 kVA

§                     It can be seen that because transformer percent impedances do not match, they cannot be loaded to their combined kVA rating. Load division between the transformers is not equal. At below combined rated kVA loading, the 4% impedance transformer is overloaded by 3.2%, while the 5.75% impedance transformer is loaded by 72%.

              Case 4: Unequal Impedance & KVA Same Ratios:

§                      This particular of transformers used rarely in industrial and commercial facilities connected to one common bus with different kVA and unequal percent impedances. However, there may be that one situation where two single-ended substations may be tied together via bussing or cables to provide better voltage support when starting large Load.

§                      If the percent impedance and kVA ratings are different, care should be taken when loading these transformers.

§                     Example: Two transformers in parallel with one 3000 kVA (kVA1) with 5.75% impedance, and the other a 1000 kVA (kVA2) with 4% impedance, each with the same turn ratios, connected to a common 3500 kVA load.

§                     Loading on Transformer-1=kVA1 = 522 / (522 + 250) x 3500 = 2366 kVA

§                     Loading on Transformer-2=kVA2 = 250 / (522 + 250) x 3500 = 1134 kVA

§                     Because the percent impedance is less in the 1000 kVA transformer, it is overloaded with a less than combined rated load.

             Case 5: Equal Impedance & KVA Unequal Ratios:

§                      Small differences in voltage cause a large amount of current to circulate. It is important to point out that paralleled transformers should always be on the same tap connection.

§                     Circulating current is completely independent of the load and load division. If transformers are fully loaded there will be a considerable amount of overheating due to circulating currents.

§                     The Point which should be Remember that circulating currents do not flow on the line, they cannot be measured if monitoring equipment is upstream or downstream of the common connection points.

§                     Example: Two 2000 kVA transformers connected in parallel, each with 5.75% impedance, same X/R ratio (8), transformer 1 with tap adjusted 2.5% from nominal and transformer 2 tapped at nominal. What is the percent circulating current (%IC)

§                     %Z1 = 5.75, So %R’ = %Z1 / √[(X/R)2 + 1)] = 5.75 / √((8)2 + 1)=0.713

§                     %R1 = %R2 = 0.713

§                     %X1 = %R x (X/R)=%X1= %X2= 0.713 x 8 = 5.7

§                     Let %e = difference in voltage ratio expressed in percentage of normal and k = kVA1/ kVA2

§                     Circulating current %IC = %eX100 / √ (%R1+k%R2)2 + (%Z1+k%Z2)2.

§                     %IC = 2.5X100 / √ (0.713 + (2000/2000)X0.713)2 + (5.7 + (2000/2000)X5.7)2

§                     %IC = 250 / 11.7 = 21.7

§                     The circulating current is 21.7% of the full load current.

             Case 6: Unequal Impedance, KVA & Different Ratios:

§                      This type of parameter would be unlikely in practice.

§                     If both the ratios and the impedance are different, the circulating current (because of the unequal ratio) should be combined with each transformer’s share of the load current to obtain the actual total current in each unit.

§                     For unity power factor, 10% circulating current (due to unequal turn ratios) results in only half percent to the total current. At lower power factors, the circulating current will change dramatically.

§                     Example: Two transformers connected in parallel, 2000 kVA1 with 5.75% impedance, X/R ratio of 8, 1000 kVA2 with 4% impedance, X/R ratio of 5, 2000 kVA1 with tap adjusted 2.5% from nominal and 1000 kVA2 tapped at nominal.

§                     %Z1 = 5.75, So %R’ = %Z1 / √[(X/R)2 + 1)] = 5.75 / √((8)2 + 1)=0.713

§                     %X1= %R x (X/R)=0.713 x 8 = 5.7

§                     %Z2= 4, So %R2 = %Z2 /√ [(X/R)2 + 1)]= 4 / √((5)2 + 1) =0.784

§                     %X2 = %R x (X/R)=0.784 x 5 = 3.92

§                     Let %e = difference in voltage ratio expressed in percentage of normal and k = kVA1/ kVA2

§                     Circulating current %IC = %eX100 / √ (%R1+k%R2)2 + (%Z1+k%Z2)2.

§                     %IC = 2.5X100 / √ (0.713 + (2000/2000)X0.713)2 + (5.7 + (2000/2000)X5.7)2

§                     %IC = 250 / 13.73 = 18.21.

§                     The circulating current is 18.21% of the full load current.

 3. Same polarity:

§                     Polarity of transformer means the instantaneous direction of induced emf in secondary. If the instantaneous directions of induced secondary emf in two transformers are opposite to each other when same input power is fed to the both of the transformers, the transformers are said to be in opposite polarity.

§                     The transformers should be properly connected with regard to their polarity. If they are connected with incorrect polarities then the two emfs, induced in the secondary windings which are in parallel, will act together in the local secondary circuit and produce a short circuit.

§                     Polarity of all transformers run in parallel should be same otherwise huge circulating current flows in the transformer but no load will be fed from these transformers.

§                     If the instantaneous directions of induced secondary emf in two transformers are same when same input power is fed to the both of the transformers, the transformers are said to be in same polarity.

4. Same phase sequence:

§                      The phase sequence of line voltages of both the transformers must be identical for parallel operation of three-phase transformers. If the phase sequence is an incorrect, in every cycle each pair of phases will get short-circuited.

§                     This condition must be strictly followed for parallel operation of transformers.

5. Same phase angle shift:(zero relative phase displacement between the secondary line voltages):

§                      The transformer windings can be connected in a variety of ways which produce different magnitudes and phase displacements of the secondary voltage. All the transformer connections can be classified into distinct vector groups.

§                     Group 1: Zero phase displacement (Yy0, Dd0, Dz0)
Group 2:180° phase displacement (Yy6, Dd6, Dz6)
Group 3: -30° phase displacement (Yd1, Dy1, Yz1)
Group 4: +30° phase displacement (Yd11, Dy11, Yz11)

§                     In order to have zero relative phase displacement of secondary side line voltages, the transformers belonging to the same group can be paralleled. For example, two transformers with Yd1 and Dy1 connections can be paralleled.

§                     The transformers of groups 1 and 2 can only be paralleled with transformers of their own group. However, the transformers of groups 3 and 4 can be paralleled by reversing the phase sequence of one of them. For example, a transformer with Yd1 1 connection (group 4) can be paralleled with that having Dy1 connection (group 3) by reversing the phase sequence of both primary and secondary terminals of the Dy1 transformer.

§                     We can only parallel Dy1 and Dy11 by crossing two incoming phases and the same two outgoing phases on one of the transformers, so if we have a DY11 transformer we can cross B&C phases on the primary and secondary to change the +30 degree phase shift into a -30 degree shift which will parallel with the Dy1, assuming all the other points above are satisfied.

6. Same KVA ratings:

§                     If two or more transformer is connected in parallel, then load sharing % between them is according to their rating. If all are of same rating, they will share equal loads

§                     Transformers of unequal kVA ratings will share a load practically (but not exactly) in proportion to their ratings, providing that the voltage ratios are identical and the percentage impedances (at their own kVA rating) are identical, or very nearly so in these cases a total of than 90% of the sum of the two ratings is normally available.

§                     It is recommended that transformers, the kVA ratings of which differ by more than 2:1, should not be operated permanently in parallel.

§                     Transformers having different kva ratings may operate in parallel, with load division such that each transformer carries its proportionate share of the total load To achieve accurate load division, it is necessary that the transformers be wound with the same turns ratio, and that the percent impedance of all transformers be equal, when each percentage is expressed on the kva base of its respective transformer. It is also necessary that the ratio of resistance to reactance in all transformers be equal.  For satisfactory operation the circulating current for any combinations of ratios and impedances probably should not exceed ten percent of the full-load rated current of the smaller unit.

7. Identical tap changer and its operation:

§                     The only important point to be remembered is the tap changing switches must be at same position for all the three transformers and should check and confirm that the secondary voltages are same. When the voltage tap need change all three tap changing switches should be operated identical for all transformers. The OL settings of the SF6 also should be identical. If the substation is operating on full load condition, tripping of one transformer can cause cascade tripping of all three transformers.

§                     In transformers Output Voltage can be controlled either by Off Circuit Tap Changer (Manual tap changing) or By On – Load Tap Changer-OLTC (Automatic Changing).

§                     In the transformer with OLTC, it is a closed loop system, with following components:

§                     (1) AVR (Automatic Voltage Regulator- an electronic programmable device). With this AVR we can set the Output Voltage of the transformers. The Output Voltage of the transformer is fed into the AVR through the LT Panel. The AVR Compares the SET voltage & the Output Voltage and gives the error signals, if any, to the OLTC through the RTCC Panel for tap changing. This AVR is mounted in the RTCC.

§                     (2) RTCC (Remote Tap Changing Cubicle): This is a panel consisting of the AVR, Display for Tap Position, Voltage, and LEDs for Raise & Lower of Taps relays, Selector Switches for Auto Manual Selection… In AUTO MODE the voltage is controlled by the AVR. In manual Mode the operator can Increase / decrease the voltage by changing the Taps manually through the Push Button in the RTCC.

§                     (3) OLTC is mounted on the transformer. It consists of a motor, controlled by the RTCC, which changes the Taps in the transformers.

§                     Both the Transformers should have same voltage ratio at all the taps & when you run transformers in parallel, it should operate as same tap position. If we have OLTC with RTCC panel, one RTCC should work as master & other should work as follower to maintain same tap positions of Transformer.

§                     However, a circulating current can be flown between the two tanks if the impedances of the two transformers are different or if the taps of the on-load tap changer (OLTC) are mismatched temporarily due to the mechanical delay. The circulating current may cause the malfunction of protection relays.

 Other necessary condition for parallel operation

1.                    All parallel units must be supplied from the same network.

2.                   Secondary cabling from the transformers to the point of paralling has approximately equal length and characteristics.

3.                   Voltage difference between corresponding phase must not exceed 0.4%

4.                    When the transformers are operated in parallel, the fault current would be very high on the secondary side. Supposing percentage impedance of one transformer is say 6.25 %, the short circuit MVA would be 25.6 MVA and short circuit current would be 35 kA.

5.                   If the transformers are of same rating and same percentage impedance, then the downstream short circuit current would be 3 times (since 3 transformers are in Parallel) approximately 105 kA. This means all the devices like ACBs, MCCBs, switch boards should withstand the short-circuit current of 105 kA. This is the maximum current. This current will get reduced depending on the location of the switch boards, cables and cable length etc. However this aspect has to be taken into consideration.

6.                   There should be Directional relays on the secondary side of the transformers.

7.                   The percent impedance of one transformer must be between 92.5% and 107.5% of the other. Otherwise, circulating currents between the two transformers would be excessive.

Summary of Parallel Operation of Transformer:

 

TransformerParallelConnection Types

Equal Loading

Unequal Loading

Overloading Current

Circulating Current

Recomm. connection

Equal Impedance & Ratio ,Same KVA

Yes

 

No

No

No

Yes

 

Equal Impedance & Ratio But different KVA

No

Yes

 

No

No

Yes

 

Unequal Impedance But Same Ratio& KVA

No

Yes

 

Yes

 

No

No

Unequal Impedance & KVA But Same Ratio

No

Yes

 

Yes

 

No

No

Unequal Impedance & Ratio But Same  KVA

Yes

 

No

Yes

 

Yes

 

No

Unequal Impedance & Ratio & different  KVA

No

No

Yes

 

Yes

 

No

 

The combinations that will operate in parallel:

§                     Following Vector group of Transformer will operate in parallel.

 

Operative Parallel Operation

Sr.No

Transformer-1

Transformer-2

1

∆∆

∆∆ or Yy

2

Yy

Yy or ∆∆

3

∆y

∆y or Y∆

4

Y∆

Y∆ or ∆y

§                     Single-phase transformers can be connected to form 3-phase transformer banks for 3-phase Power systems.

§                     Four common methods of connecting three transformers for 3-phase circuits are Δ-Δ, Y-Y, Y-Δ, and Δ-Y connections.

§                     An advantage of Δ-Δ connection is that if one of the transformers fails or is removed from the circuit, the remaining two can operate in the open-Δ or V connection. This way, the bank still delivers 3-phase currents and voltages in their correct phase relationship. However, the capacity of the bank is reduced to 57.7 % (1 3) of its original value.

§                     In the Y-Y connection, only 57.7% of the line voltage is applied to each winding but full line current flows in each winding. The Y-Y connection is rarely used.

§                     The Δ-Y connection is used for stepping up voltages since the voltage is increased by the transformer ratio multiplied by 3.

 The combinations that will not operate in parallel:

§                     Following Vector group of Transformer will not operate in parallel.

 

Inoperative Parallel Operation

Sr.No

Transformer-1

Transformer-2

1

∆∆

∆y

2

∆y

∆∆

3

Y∆

Yy

4

Yy

Y∆

 To check Synchronization of Transformers:

§                     Synchronization of Transformer can be checked by either of following steps:

§                     Checked by synchronizing relay & synchro scope.

§                     If Secondary of Transformer is not LT Then we must use check synchronizing relay & Commission the system properly. After connecting relay. Relay must be charges with only 1 supply & check that relay is functioning properly.

§                     Synchronizing should be checked of both the supply voltages. This can be checked directly with millimeter between L1 phases of Transformer 1 and L1 phase of Transformer 2. Then L2 Phase of Transformer 1 and L2 Phase of Transformer 2. Then L3 Phase of Transformer 1 and L3 Phase of Transformer 2. In all the cases MultiMate should show 0 voltages theoretically. These checks must be done at synchronizing breakers only. We have to also check that breaker out going terminals are connected in such a way that L1 Terminals of both the Breakers comes to same Main Bus bar of panel. Same for L2 & L3.

§                     Best way to check synchronization on LT is charge complete panel with 1 source up to outgoing terminals of another incoming breaker terminal. Then just measure Voltage difference on Incoming & out going terminals of Incoming Breaker. It should be near to 0.

§                     To check circulating current Synchronize both the transformer without outgoing load. Then check current. It will give you circulating current.

Advantages of Transformer Parallel Operation:

1)     Maximize electrical system efficiency:

§                     Generally electrical power transformer gives the maximum efficiency at full load. If we run numbers of transformers in parallel, we can switch on only those transformers which will give the total demand by running nearer to its full load rating for that time.

§                     When load increases we can switch no one by one other transformer connected in parallel to fulfil the total demand. In this way we can run the system with maximum efficiency.

2)     Maximize electrical system availability:

§                     If numbers of transformers run in parallel we can take shutdown any one of them for maintenance purpose. Other parallel transformers in system will serve the load without total interruption of power.

3)     Maximize power system reliability:

§                     If nay one of the transformers run in parallel, is tripped due to fault other parallel transformers is the system will share the load hence power supply may not be interrupted if the shared loads do not make other transformers over loaded.

4)     Maximize electrical system flexibility:

§                     There is a chance of increasing or decreasing future demand of power system. If it is predicted that power demand will be increased in future, there must be a provision of connecting transformers in system in parallel to fulfil the extra demand because it is not economical from business point of view to install a bigger rated single transformer by forecasting the increased future demand as it is unnecessary investment of money.

§                     Again if future demand is decreased, transformers running in parallel can be removed from system to balance the capital investment and its return.

Disadvantages of Transformer Parallel Operation:

§                     Increasing short-circuit currents that increase necessary breaker capacity.

§                     The risk of circulating currents running from one transformer to another Transformer. Circulating currents that diminish load capability and increased losses.

§                     The bus ratings could be too high.

§                     Paralleling transformers reduces the transformer impedance significantly, i.e. the parallel transformers may have very low impedance, which creates the high short circuit currents.
Therefore, some current limiters are needed, e.g. reactors, fuses, high impedance buses, etc

§                     The control and protection of three units in parallel is more complex.

§                     It is not a common practice in this industry, since Main-tie-Main is very common in this industry.

 Conclusions:

§                      Loading considerations for paralleling transformers are simple unless kVA, percent impedances, or ratios are different. When paralleled transformer turn ratios and percent impedances are the same, equal load division will exist on each transformer. When paralleled transformer kVA ratings are the same, but the percent impedances are different, then unequal load division will occur.

§                     The same is true for unequal percent impedances and unequal kVA. Circulating currents only exist if the turn ratios do not match on each transformer. The magnitude of the circulating currents will also depend on the X/R ratios of the transformers. Delta-delta to delta-wye transformer paralleling should not be attempted.

 References

§                     Say, M.G. The performance and design of alternating current machines.

§                     Application Guide, Loading of Transformer, Nashville, TN, USA.

§                     Toro, V.D. Principles of electrical engineering.

§                     Stevenson, W.D. Elements of power system analysis.

§                     MIT Press, Magnetic circuits and transformers, John Wiley and Sons.

Parallel Transformers: Balancing Act

Second Wind, parallel transformersFrom Electrical World Magazine, "Engineer’s Notebook" by Walter Sass

 While there are few conceptually simpler ways to get more useful capacity from transformers than to strategically parallel them, in reality, transformer paralleling is anything but simple. For example, two 40–MVA transformers could not individually service two buses with 10– and 50–MVA loads. They could if they were tied together, but virtually any difference between them (from winding variations to MVA ratings) could lead to equipment overloads, wasted energy, and operational instability.

Parallel configurations where the primaries are connected to different buses, pose even graver difficulties. And combining voltage–regulating controls that were designed to work on independent transformers may not work at all.


Power supply sharing is one of the oldest and most persistant problems in electrical engineering. Whether the power sources are transistors or hydro–electric generators, problems arise when their outputs get connected together.

For example, it might be tempting to combine two independent circuits, each consisting of one battery powering one lightbulb, to best distribute the energy from both batteries. The combined circuit of parallel batteries and bulbs might work, but there may be unintended consequences. The stronger battery may charge (dump energy into) the weaker one. How much source–to–source energy transfer takes place is a function of the source impedances and voltage characteristics. In specific cases, such as identical batteries with identical states of discharge, there might be no source–to–source currents. Otherwise, the undesired energy transfer would occur unchecked, unless some form of regulating circuitry – like blocking diodes for example – stopped it.

In the case of output–interconnected distribution transformers, undesired energy transfer can similarly occur. Unlike the battery example, there is no possibility of adding diodes or other regulating circuits. In fact, the only regulating means available are usually the load tap changers (LTCs) that regulate the line voltages going to the loads.

LTCs can’t change transformer impedances or block currents, and their primary line regulation functions cannot be ignored, so their effectiveness in facilitating transformer paralleling is inherently limited. In fact, transformers with substantial impedance differences (10% or greater expressed on the same base) may not be paralleled safely.

But let’s assume it’s possible to use sophisticated controls to operate paralleled LTCs to somehow optimally minimize energy transfer (circulating current) and maintain line regulation. In the example above, this would be equivalent to paralleling two batteries by adjusting small series potentiometers to match voltage outputs of each. The pots could be adjusted jointly to regulate the voltage going to the lightbulb loads, and adjusted differentially to reduce circulating current between the batteries.

Unfortunately, AC power circuits are more complicated. Using LTCs to regulate the output voltages of parallel transformers primarily acts to share reactive power (VAr) between them, not real power. The optimal paralleled LTC control scheme may be required to restrict VAr burdens on each transformer, further compromising its ability to distribute the real power loads as intended.

Despite these problems and limitations, transformer paralleling is becoming an increasingly common utility practice. Even if inevitable circulating currents waste energy and heat up the transformers, or if shifted VAr burdens run the transformers nearer their VA limits, the possibility of picking up more load with existing equipment is very compelling.

The key to operating transformers in parallel safely will be more LTC control strategies that truly optimize line regulation, minimize circulating currents, and limit VAr burden. Such control strategies will require distributed observation of bus interconnections at the substation and coordinated operation of LTCs that bypass or eliminate their local controllers. Further, transformer manufacturers can expect their gear to run hotter and experience more overstress as paralleling becomes more common.

50 MVA 138KV AUTOTRANSFORMER SPECIFICATION SAMPLE


Type:    Outdoor use, Oil-immersed, OA/FA/FA, 3 Windings with rubber diaphragm
             conservator vented via silica gel dehydrating breather, On-load-tap changer,  
             manufactured according to ANSI C57.12.00 Std., All Copper Windings,                                                         
            For use as a Step-down transformer in an electric utility transmission substation.
           Complete with standard accesories.

Rating: 
              HV    -     30/40/50 MVA
              LV    -      30/40/50 MVA
             TV    -      12/16/20 MVA

Cooling Method:  OA/FA1/FA2

Rated Voltage:      HV -  138KV
                            LV -    69KV
                            TV -   13.2KV

Tap Voltage:   HV Side OLTC: 138 KV + 8, - 12 x 1.0%,  21 Taps


OLTC: ABB type UZFRT 550/300, 138,000 Volts, 
             3 Phase, 60 Hz, 21 positions,

            With Motor Drive Mechanism type BUF 3,
            Motor : 460 Volts, 3 Phase, 60 Hz
            Contactors: 230 Volts AC,
            Position Transmitter: 230 Volts AC
            Heating Element      : 230 Volts AC
            With Manual/Automatic Change over-switch,  Raise & Lower pushbuttons.
           
BIL:
      Winding             :    HV      –  650 KV
                                  LV       -  350 KV
                                  Neutral – 150 KV
                                TV       -  110 KV

     Bushing               :  HV        -  650 KV
                               LV        -  350 KV
                                 Neutral   - 150 KV
                                   TV          - 150 KV

Frequency : 60 Hz
Connection:
            HV  -  Star with Neutral (Auto-Star) brought out to a bushing
            LV  -   Star with Neutral (Auto-Star) brought out to a bushing
            TV  -   Delta

Vector Group : Yyna0d1

Guaranted Losses at rated voltage, frequency, unity pf & @ 85 deg C (50 MVA):        
          No -Load Loss:               18.6 KW
          Load Loss @ 50 MVA:   157.6 KW
         Efficiency :                       99.65% @ 50 MVA( Without Auxiliary Loss)

Temperature Rise Limits:
             Oil         -  65 deg C
             Winding – 65 deg C

% Impedances  @ 85 deg
                  HV – LV@ 50 MVA        HV - TV@ 20 MVA       LV - TV@ 20 MVA
         8L    -   149,040 V   -   10.28            -       10.45
         N     -   138,000 V   -   10.50            -       10.31              -            5.6          
       12R   -   121,440 V   -   11.09            -       10.52
     
            
Audible Sound Level @ 50 MVA with all fans running: 72dB

Service Condition:
                Maximum ambient air temperature:                                             40 deg C
                Average ambient air temperature for any 24h period:                  30 deg C
                Maximum altitude above sea level:                                             1000 meters
               Maximum ambient relative humidity:                                            88%
                Mean annual rainfall:                                                                  2400 mm
               Maximum wind velocity:                                                             220 km/hr
               Maximum seismic factor:                                                            0.45g

CONSTRUCTIONS
      
a) Core:
The core of the transformer will be constructed of the highest quality, non-aging high permeability, cold-rolled gain-oriented  silicon steel sheet especially suitable for the purpose. Every care will be taken during slitting and cutting process to avoid burrs. Both sides of each sheet will be special glass film insulated on to minimize eddy current losses. The cores will be carefully assembled and rigidly clamped to ensure adequate mechanical strength to support the windings and also reduced vibration to minimum under operating conditions.
      b) Windings:
                       The winding of the transformer shall be made of  high tensile strength electrolytic copper of a high conductivity (Class A, in accordance with ANSI) 
                       and insulation material of high quality shall be used. The windings shall be  free from burrs, scales and splinters.
 
The insulation material of windings and connections shall not shrink, soften or collapse during service. Thermally upgraded paper shall be used for conductor insulation. The design, construction and treatment of windings shall give proper consideration to all service factors, such as high dielectric and mechanical strenght of insulation, coil characteristics, uniform electrostatic flux distribution, prevention of corona formation, and minimum restriction to oil flow.

Moreover, under any load condition, none of the material used shall disintegrate, carbonizer or become brittle under the action of hot oil.

The coils must be capable of withstanding movement and distortion caused by abnormal operating conditions. Adequate barriers shall be provided between windings and core as well as between high voltage and low voltage windings. All leads or bars from the windings to the terminal boxes and bushings shall be rigidly supported. Stresses on coils and connections must be avoided.

Due to very unfavorable short-circuit conditions and numerous short-circuits in the network, special measures have to be taken to increase the capability of the winding to withstand short-circuit currents. Winding and arrangement of coils shall be designed so as to unify the initial potential distribution caused by impulsive traveling waves, as much as possible, to avoid potential oscillation and in order to withstand abnormal high voltage due to switching.

To increase the capability of the transformer windings to witstand electromagnetic forces under short circuit conditions, modern technology in design and construction shall be applied. (e.g. low current density, provision of pressure limiting devices and spring elements, use of perfectly dried pre-compressed pressboard, maintaining a balance of ampere-turns between windings, ets.)

Measures against coil displacement as generated by the radial and longitudinal forces shall be considered. Computation of strength against these forces including the description of the method being applied shall be submitted in detail.

The tank, conservation, coolers and bushings shall be adequately braced to withstand ocean shipment, and earthquake with seismic coeffecient of 0.45 g (horizontal)

c)   Short Circuit Withstand Capability
The transformer shall withstand the combined effects of thermal, mechanical and electromagnetic stresses arising under short-circuit conditions based on the maximum durations of fault:

Primary  Winding:  2 seconds

Secondary  Winding:  2 seconds

Tertiary    Winding                    2          seconds

The maximum sustrained short-circuit current in each windings shall be stated by the manufacturers. The maximum temperatures of the windings shall not exceed 250 deg C within the seconds duration of fault. All transformer accessories, parts, components (CT's, bushings, tap-changer, etc.) shall be capable of withstanding the cumulative effects of repeated mechanical and thermal over-stressing as produced by short-circuits and loads above the nameplate rating.

For design purposes, the following network data shall be take into consideration. The available system fault currents as as follows (in rms):

138 KV: Ik"  60 KA         69 KV : Ik" = 50 kA  13.2 KV : Ik" = 40 kA

The transformer shall be capable of withstanding the resulting successive short-circuits, without cooling to normal operating temperature between successive occurence of the short-circuit, provided the accumulated duration of short-circuit does not exceed the maximum duration permitted for single short-circuit defined above.

The upper limits of the symmetrical overcurrent due to such short-circuits as a multiple of rated current shall also be specified by the manufacturer.

      d)  Overload Capability
The short-time overload rating and operation of the transformer shall be in accordance with ANSI C57.92 or IEC 354. All other auxiliary equipment (bushings, CT's, etc) affected shall be rated to match the transformer overload rating.

e) Transformer Tanks:
 The tank should have sufficient strength to withstand full vacuum and internal pressure of 1.0 kg/cm2, with cooling equipment & conservator connected. The tank cover will be clamped with bolts and nuts, and will be provided with handhole or manholes of suitable size. All seams and jointwill be oil tight. Guides within the tank will be furnished to facilitate tanking and untanking, and to prevent movement of the core and coil assembly, in transit. The casing will be provided with suitable lugs for lifting the completely assembled transformer filled with oil. All gaskets will be synthetic rubber bonded cork.

f) Radiators:
 The transformer will be provided with a number of sufficient radiators for self-cooled (OA) operation. The radiator will be installed on the tank via radiator valves, so that each radiator can be detached from the tank independently of the oil in the main tank. The radiator valves will have the open and close positions clearly marked. Radiators will be equipped with provisions for draining. Radiators shall be made of galvanized steel.

g) Forced-air-cooling system:
 For forced-air-cooled (FA) operation, the transformer will be provided with automatically controlled three phase motor-fans actuated from winding temperature. Fan motor, weather proofed, three phase, Hz, and will be thermal protected. The cooling-fans will be mounted on the radiators and the control box will be mounted on the wall of the tank. Motor Voltage: 460 VAC, 3 phase, 60 Hz.

h) On-load tap-changer:
The following tap-changer will be equipped on H.V. side for the regulation of voltage under loading conditions.
   Type    Type UZFRT 550/300
                              3 phase,60 Hz, 21 positions
   Number of tap positions           21 taps positions
                                                                                   (138KV + 8 X 1380 V, - 12 X 1380 V)
                                   Manufacturer   ABB

                                    Motor Drive Mechanism:
                                    Type:                                        ABB type BUF 3
   Motor Voltage:   460 Volts, 3 Phase, 60 Hz
                                    Contactors Voltage:                  230 VAC
                                    Position Transmitter:                 230 VAC
                                    Heating Element:                       230 VAC
                             
                            Motor-Drive Mechanism Accessories:
                                   1. Standard Accessories
                                   2. Phase Failure Relay
                                   3.Circuit Breakers for Control & Auxiliary circuits
                                   4. Accessories for paralleling with 2 transformers using MASTER-FOLLOWER method.

                          OLTC Accessories:
                                   1.  Oil Conservator
                                   2.  Oil Level Indicator with contacts for Alarm
                                   3.
 Dehydrating Breather
                                   4.  Pressure Relief Valve/Device with contacts for tripping
                                   5.
 Pressure Relay with contacts for tripping
                                   6. Oil Flow Controlled Relay with contacts for alarm
                                   6.
Thermoswitch Housing
                                   7.
Valve for oil filtration mounted on the top
                                   8. Valve for oil filling, draining & filtration
                                   9.
Earthing terminal
                                  10.
Prepared for on - line oil filter unit

  

i) Oil preservation system:
Conservator system with sealed diaphragm will be used. Conservator with low-profile design having a moisture-proof barrier made with an oil-resisting diaphragm will be applied and placed at the level slightly higher than the transformer tank.

j) Bushings:
  Primary:          ABB type GOB 650-1250-0.3 Brown, Cat # 123 193-K
                                              1250 Amps, Nominal Voltage: 170 KV rms,
                                               Phase to Earth Voltage:145 KV rms, BIL: 650KV,
                                               Creepage Distance: 4080 mm
                                               Porcelain Color: Brown
                                               Short end shield

  Secondary:       ABB type GOB 380-800-0.3 Brown, Cat # 123-185-K 
               800 Amps, Nominal Voltage: 100 KV rms,
                                                Phase to Earth Voltage:72.5 KV rms, BIL: 380 KV
                                                Creepage Distance:2210 mm
                                                Porcelain Color: Brown
                                                Short end shield

                       Tertiary:           CEDASPE s.p.a. Italy type Dt 30 Nf 1000
                                              1000 Amps, Nominal Voltage: 36 KV,
                                               Maximum Voltage to Ground: 30 KV, BIL:170 KV,
                                               Creepage Distance: 640 mm
                                               Porcelain Color: Brown
                                               Threaded Extended Rod

                      Neutral:            CEDASPE s.p.a. Italy type Dt 52 Nf 1000
                                              1000 Amps, Nominal Voltage: 52 KV
                                              Maximum Voltage to Gound: 52 KV, BIL 250 KV,
                                              Creepage Distance: 1080 mm
                                              Porcelain color: Brown
                                             Threaded Standard Rod


Complete with the following accessories:

31.  One (1) Buchholz Relay with 2 contacts for alarm & tripping
32.
 Two (2) Dial type Oil Level Indicators for Main Tank & OLTC with contacts for alarm.
33.  One (1) Oil Temperature Indicator & Relay type AKM OTI series 34 for alarm.
34.  Three ( 3) Winding Temperature Indicators & Relays for HV, LV & TV windings with
        3 contacts each for alarm, tripping & fan control, AKM type WTI series 35.
35.  Qualitrol type self resetting mechanical Pressure Relief Device with contacts for tripping
36.  Conservator for main Tank - Sealed Diaphragm constant pressure type.
38.  Breather type conservator for OLTC.
39.  Annunciators (Marshalling Kiosk)
40.  Bushing Current Transformers
         HV:     300/200/100:5A;    0.6 - B 0.5
         LV & Neutral:  600/500/400/300/200/100:5A;   C-400
         TV :    1200/1000/900/800/600/500/400/300/200/100:5A;  C-400
        

41.     Galvanized Steel Radiators

42.
    Bushing Terminals

         HV- Universal 4 hole NEMA Flat Terminals
         LV- Universal 4 hole NEMA Flat Terminals
         TV – Universal Multi -hole NEMA Flat Terminals

43.   Sets of Surge Arresters mounted nearest to the HV, LV & TV transformer bushings,
       with Surge Counters & 4/0 AWG THW Copper conductors connected 
       to grounding terminals.                                                                                                                                                                              


HV     : 120 KV Voltage Rating, 98 KV MCOV, Station Class, Polymer housing,       
        Metal Oxide, Line Discharge Class 4 per IEC, 12 KJ/KV Energy capability
        65 KA Pressure Relief Capability, Grey Silicone Insulator
        ABB type PEXLIM-P
        Complete with top clamps to hold a 336.4 MCM Aluminum Conductor
and 4/0 AWG THW Copper green wire ground conductor connected to ground terminal.

       LV     : 60 KV voltage Rating, 48 KV MCOV, Station Class, Polymer housing, Metal
        Oxide, Line Discharge Class4 per IEC, 12 KJ/KV Energy Capability
        65 KA Pressure relief Capability, Grey Silicone Insulator,
        ABB type PEXLIM-P
        Complete with top clamps to hold a 795 MCM Aluminum Conductors
        and  a 4/0 AWG THW Copper green wire ground conductor connected
        to ground terminal.

       TV     : 18 KV Voltage Rating, 15 KV MCOV Station Class, Polymer housing,
        Metal Oxide, Line Discharge Class 3 per IEC, 9.0 KJ/KV energy capability
        65 KA pressure relief capability, Grey Silicone Insulator,
        ABB type POLIM-S 15N
                   Complete with top clamps to hold a 795 MCM Aluminum Conductors
        and a 4/0 AWG THW Copper green wire ground conductor connected to
        Ground terminal.

44.    Neutral Conductor: 4/0 AWG THW Copper wire colored green connected to
         ground pad.

45.   Insulating Oil – Shell Diala B or equivalent

46.  With provision for Built-in OLTC Insulating Oil Filter Machine, such as mounting
        brackets, connecting flange, connecting valves, etc.

47.  Cooling Fans must be 3 Phase, 460 VAC, 60 Hz, Winding Temperature Controlled
        for Automatic Operation, with automatic/manual change over switch.
       With Circuit breakers for motor overload & short circuit protection.

48.  Grounding Pads for HV Arresters,
LV Arresters, TV Arresters & Neutral Cables.

49.  Steel Ladder with caution marking

50.  All External Power & Control cables must be flexible, multicore,  PVC insulated
       & enclosed in conduit pipes & flexible hoses.

51.  All power & control circuits must be protected by circuit breakers.

52. Welded Tank Cover.

53. All wiring connections & terminations must be ANSI standard using crimp type
       terminal lugs with insulator caps.

54.  All wirings must be color-coded.

55.  With replacement gaskets

56.  Anchor Bolts

57. One (1) Spare bushing each for HV, LV & TV

58.
One (1) Spare OLTC Tap Position Indicator for remote use

59. With provisions for parallel operation of existing power transformer using
      Master - Follower method of OLTC Control.

        
60. TESTS:
      The following tests shall be carried out at the factory with the presence
      of user representative and records of testing will be submitted.
         a. Winding  Resistance Tests
         b. Turns Ratio Tests
         c. Polarity & Phase Relation Tests on rated voltage
        d. Measurement of no-load losses and excitation current @ 90%, 100%
           & 110% of rated secondary voltage @ rated frequency
           rated voltage connection.
        e. Measurement of impedance voltage and load loss tests at rated current
           and rated frequency.
        f. Low frequency tests (Applied Voltage & Induced Voltage) including
           partial discharge measurement in terms of RIV.
        g. Leak Test.
        h. Routine test certificate for the bushings, current transformers and surge
            arresters shall be submitted.
        i. Temperature Rise Test at OA, FA1 & FA2 ratings on the tapping
          with maximum losses.
       j. Lightning Impulse Test on HV,
LV , Neutral & Tertiary terminals.
        (Full wave, Chopped wave & reduced full wave)
      k. Audible Sound level Test at no-load and rated frequency and
         with all fans operating.
            l.  Measurement of zero-sequence impedance.
           m. Insulation Power factor
           n.  Insulation Resistance Tests at ambient temperature.
           o. Vacuum test on transformer tank, conservator & radiators; and pressure
               test on tank and oil-filled compartments.
           p. Determination of Capacitances (windings to ground & between windings)
          q.  Tests on auxiliary equipment & accessories ( functional tests
               including cooling control)
           r.  Voltage regulation
          s. Measurement of the power taken by the fan and oil pumps motors.
          t. Functional tests on Tap Changer
          u. Test on Current Transformers ( Check on polarity, ratio & wiring)
          v. Mechanical inspection, ( check of layout, dimensions, nameplate
             data, clearances, etc)
         w. Oil tests
         x. Efficiency at principal tap and full load for unity & 0.8 power factor.
       
61.  SPECIAL TEST
       Certificate of Short Circuit Test on power transformers of similar rating
       shall be submitted. 
   
62.  Other Accessories, Tools

    a. Pressure gauge with nitrogen tube and automatic filling device which
         fill the transformert through the tube in case of any leakage shall
         be supplied.
    b. Three-dimensional impact recorder with time period recording chart of
        at least 3 months for use during transport of the transformers.
    c. Silica -gel breathers for main and OLTC conservators.
  
63.  Painting
      Special attention should be given to the protection of all iron-work.
      The methods propised and the means adopted should be fully described
      in the offer.

     All surfaces shall be thoroughly cleaned of rust, scale, grease and dirt and
    other foreign matters and all imperfections shall be removed by means
    of approved methods.

     The following treatments shall be applied:

     a.  External surfaces

           All steel surfaces shall be sand-blasted in accordance with SIS 055900,
          and shall then be painted in the following sequence:
        
            1. two (2) primer coats:                      2 x 35 um (micrometer)
           
            Binder  : epoxy resin hardened with polyamide              
                  Pigment: titanium dioxide, zinc oxide, zinc phosphate, tinting additives

                  2. one (1) intermediate coat:               35 um
 
                 Binder:  epoxy resin hardened with polyamide
                 Pigment: titanium dioxide, micaceous iron oxide, tinting additives

                 3. one (1) top coat (polyurethane base):   35 um

                 Binder:  epoxy resin hardened with isocyanat
                 Pigment: titanium dioxide, micaceous iron oxide, tinting additives

                 Coating thickness:                   Total        140um

                 The color code shall be Munsell Gray No. N7.0

        b. Internal surfaces
   
                Inside the transformers vessel, sand-blasting shall be performed in
               accordance with SIS 055900. After that solvent-free,
               oil-resistant coating shall be applied.

               The minimum dry film thickness shall be 40 um.

You might also like:

50 MVA 138KV AUTOTRANSFORMER SPECIFICATION SAMPLE

AUTOTRANSFORMER CONNECTIONS BASIC AND TUTORIALS

VOLTAGE ACROSS AUTOTRANSFORMERS BASIC INFORMATION AND ...

AUTOTRANSFORMER CONNECTIONS BASIC AND TUTORIALS

 

LinkWithin

  

No comments:

Post a Comment

Links to this post

Newer PostOlder PostHome

Subscribe to: Post Comments (Atom)

Previous Articles

·                     ▼  2012 (166)

o                                            ►  November (11)

o                                            ►  October (5)

o                                            ►  September (12)

o                                            ►  August (13)

o                                            ►  July (6)

o                                            ►  June (18)

o                                            ▼  May (17)

§                                                                     IMPEDANCE MATCHING TRANSFORMER SELECTION BASIC AND...

§                                                                     RESISTANCE TYPE TRANSFORMER LOAD TAP CHANGER BASIC...

§                                                                     INSTRUMENT TRANSFORMER METERING IN METALCLAD SWITC...

§                                                                     TYPES OF FAILURES IN POWER TRANSFORMERS BASIC AND ...

§                                                                     THE NATURE OF TRANSFORMER LOSSES BASIC INFORMATION...

§                                                                     AUTOTRANSFORMER CONNECTIONS BASIC AND TUTORIALS

§                                                                     POWER TRANSFORMER TEMPERATURE RISE AND THE THERMAL...

§                                                                     POWER TRANSFORMER SERIES IMPEDANCE AND REGULATION ...

§                                                                     ON LOAD TAP CHANGER DESIGN TEST FOR MOTOR DRIVEN M...

§                                                                     ON LOAD TAP CHANGER NAMEPLATE SAMPLE AND REQUIREME...

§                                                                     TESTING OF PHASE SHIFTING TRANSFORMERS BASIC AND T...

§                                                                     PHASE SHIFTING TRANSFORMER USUAL SERVICE CONDITION...

§                                                                     TRANSFORMER PERCENT (%) REGULATION BASIC AND TUTOR...

§                                                                     TRANSFORMERS TAPPING BASICS AND TUTORIALS

§                                                                     50 MVA 138KV AUTOTRANSFORMER SPECIFICATION SAMPLE

§                                                                     HIGH PERMEABILITY STEEL USED IN TRANSFORMER CORE B...

§                                                                     OPEN DELTA CONNECTION FOR LIGHT AND POWER BASIC AN...

o                                            ►  April (18)

o                                            ►  March (23)

o                                            ►  February (28)

o                                            ►  January (15)

·                     ►  2011 (4)

http://www.powertransformerdesign.net/2012/05/50-mva-138kv-autotransformer.html

I wish to present here the benefits of utilization and operation of MV/LV  in . Having such experience, i will be interested to get feedbacks from other engineers.

2 MV/LV parallel transformers distribution network

2 MV/LV parallel transformers distribution network

For all my experience, I’ve never met a working electrical installation, where operation of parallel transformers was used. Once, we used this solution in the design of welding shop, mainly to reduce the  in the network and maintain a stable level of short-circuit current. But the project was stopped by the Employer, and the idea was gone. Below is the list of benefits of such solution, as it is seen. It would be great if interested engineers commented and shared experiences on this issue.

Generally, application of parallel transformers allows achieving the following benefits:

1) Reducing the total capacity of  (as compared to separate their work). The decrease of total installed capacity is reached:

·                     by lowering the overall  demand load to the diversity of loads connected to different transformers

·                     by using a higher load rate of parallel transformers

·                     less required backup in case of electrical transformer failure

2) Reduction of electricity losses in electrical transformers due to a possible disconnection of unloaded transformers

3) Improving the  due to the stable level of short circuit current throughout the network

4) Increasing the reliability of operation of protective devices in the case of phase-to-earth short circuits in the network.

5) Possibility of placing electrical transformers in operation phase-by-phase

Parallel transformers are allowed, provided that none of the windings will be loaded by current exceeding allowable current for that winding.

Of course, there are limitations for using electrical transformers connected in parallel. For instance, Russian Federation “Rules for technical maintenance of electrical consumers” allows operation of parallel transformers under the following conditions:

·                     windings connections of transformers have the same vector groups

·                     the ratio of transformers capacities of less than 1.3

·                     rates of transformation differ by no more than +/-0.5%

·                     short circuit voltages do not vary more than +/-10%

·                     transformers have same phase polarity

Artem Kropachev

Related posts

·                     Stability Factor: K-Factor (2)

·                     Software for electrical installation (80)

·                     Power factor correction kvar policy in countries (23)

·                     Parallel transformer electrical distribution (10)

·                     Harmonics overview (10)

You enjoy this post:

 

 

 

 HARYANA VIDYUT PRASARAN NIGAM LTD.

 

 

 

 

 

SPECIFICATION  NO. SSD/S-08/DGM-1386

 

 

 

 

 

 

TECHNICAL SPECIFICATION

 

 

 

 

 

FOR

 

 

 

 

 

40/50MVA, 132/33 kV POWER TRANSFORMER

 

 

 

 

           CHIEF ENGINEER/MM,    

           HVPNL, SHAKTI BHAWAN,

           SECTOR-6, PANCHKULA.  

 

 

                                                    JULY-2012

                                                  TECHNICAL SPECIFICATION FOR

40/50 MVA 132/33kV

POWER TRANSFORMER

1.00     SCOPE:

a)         This specification covers the Design, Engineering, manufacture, testing, supply on CIP basis, transportation to site, insurance, storage, testing and commissioning of 40/50 MVA 132/33 kV Power Transformers.

b)         All drawings, schedules and annexures appended to this specification shall form part of the specification and supplement the requirements specified. The equipment/materials offered by the Bidder shall be complete in all respects and, whether called for specifically or not, all accessories, hardware and services required for normal satisfactory operation of the system shall be deemed to be included in unit rates quoted. Design and manufacture shall also be such that equipment/ accessories of the same type and rating would be interchangeable.

Specific reference in this specification and documents to any material by trade name, make or catalogue number shall be construed as establishing standard of quality and performance and not as limiting competition. All equipment/ accessories offered shall also be of proven design and manufacture. The make of all accessories and hardware shall be subject to purchaser’s approval.

2.00     CODES & STANDARDS:

All standards, specifications and codes of practice referred to herein shall be the latest editions including all applicable official amendments and revisions as on date of opening of bid.  The following standards and codes shall be applicable: -

IS:5                 Colour for ready mix paints.

IS:325                         Three phase induction motors.

IS:335                         New insulating oils for transformer.

BS:148/IEC-296

IS:375              Marking & arrangement of Switch-gear bus bars main connections and auxiliary wiring.

IS:1866           Code of practice for maintenance of insulation oil

IS:2026           Specification for Power Transformers.

&IEC:76

IS:2099           Bushing for alternating voltages above  1000 volts

& 3347

IS:2147            Degree of protection provided by enclosures for low voltage switchgear & control gear.

IS:2705           Current transformer

IS:3637           Gas operated relay.

IS:3639           Fittings and accessories for Power Transformers.

IS:6600           Guide for loading of oil immersed transformers.

&IEC-354

IS:8468            On load tap changer.

&IEC:214

IS:5561            Electric power connectors.

IS:617              Aluminium Alloy grade.

IS:2629            Recommended practice for hot-dip Galvanising.

IS:8478            On load tap changer application guide.

IS:8603            Dimensions for porcelain transformer bushings for use in heavily polluted atmosphere(36 kV Class). Dimensions for oil filled porcelain transformer bushings for use in medium polluted atmosphere.

IS:9434            Guide for sampling and analysis of free and dissolved gas in oil filled equipment.

IS:10028          Code of practice for selection, installation and  maintenance of transformers.

IS:12676          Dimensions for OIP insulated condenser bushings.

CBIP                Manual on transformer.

Equipment complying with other internationally accepted standards will also be considered if these ensure performance and constructional features equivalent or superior to standards listed above.  In such a case the Bidder shall clearly indicate the standards adopted, furnish a copy in English of the latest revision of standard alongwith copies of all official amendments and revisions in force as on date of opening of bid and clearly bring out the salient features for comparison.

3.0              CLIMATIC CONDITIONS:

The transformers are required to operate satisfactorily under the following site conditions:

            3.1       Max. temperature                                                                  50 C

            3.2       Min. temperature                                                                   -2.5 C

            3.3       Max. relative humidity                                                            100%

            3.4       Min. relative humidity                                                             26 %

            3.5       Average number of rainy days per annum                Nearly120 days

            3.6       Average annual rain fall                                                         900mm

            3.7       Average number of dust storm days per annum.                 35

            3.8       Isoceraunic level                                                                   45

            3.9       Max. Wind pressures                                                195 kg/sqmt.

            3.10     Altitude above mean sea level                                  Less than 1000 mt.

 

4.0              TYPE AND RATING :

4.1       The transformer shall be of two winding, 3 phase oil immersed core type with ONAN/ONAF cooling suitable for outdoor service as step down transformers. The transformer shall not be provided with the tertiary delta winding.

4.2       The ratings and other characteristics which are not covered elsewhere shall be, as detailed in following clauses:

4.2.1    Max. Continuous capacity:

a)        ONAN                                     40 MVA

b)        ONAF                                     50 MVA

4.2.2    Number of phases                                3

4.2.3    Frequency                                         50 Hz

                      (±5%)

4.2.4        Rated Voltage :

a)        HV side                                   132kV 

b)        LV side                                   33kV   

4.2.5    Connections :

a)        HV side                                   Star

b)        LV side                                   Star

4.2.6    Vector group                                      YYO

4.2.7    %age Impedance                               10% at

                                                                      50 MVA base

4.2.8    ON load taps on HV side +5% to -15% in steps of 1.25% each

4.2.9    a)        Insulation level                        132 kV             33 kV

i)         Lighting withstand                  550 kV             170kV

ii)                   Power frequency                   230 kV             70 kV

withstand voltage                  (rms)               (rms)  

b)        Insulation level of Bushings

i)         Lighting Impulse                     650 kV            170kV

voltage

ii)         Power frequency                    275 kV             70 kV

voltage                                               (rms)              (rms)

4.2 10  Total Creepage Distance :   

a)                  Total: 25mm per kV corresponding to highest system voltage i.e.
145 kV, 36 kV, 12 kV.

b)                  Protected: 50% of the total Creepage distance      

5.         GENERAL DESIGN OF TRANSFORMER: -

5.1       The transformer and accessories shall be so designed as to facilitate inspection, cleaning and repairs.  The requirement of Indian Electricity Rules shall be kept in view.

5.2       The design shall ensure satisfactory operation under severe working conditions due to fluctuating load of steel furnaces and voltage variations in the system including those, due to short circuits.  The transformers shall be designed as to minimize the risk of accidental short circuits  caused by animals, birds or vermins.

            The design shall incorporate every reasonable precaution and provision for the safety of all those concerned in the operation and maintenance of the equipment keeping in the view the requirement of Indian Electricity Board.

5.3       All material used shall be of the best quality and of class most suitable for working under specified conditions and shall withstand the atmospheric conditions and temperature variations without undue deterioration or distortion or setting up of undue stress in any part thereof.

5.4       Cast iron shall not be used for any parts other than the radiator valve bodies.

5.5       Corresponding parts liable to replace shall be interchangeable.

5.6       All taper pins to be used in the mechanism shall be split types as per latest edition of IS: 2393.

5.7       All mechanism should be rust and corrosion proof.  Means shall be provided for lubrication of moving parts not immersed in oil.

5.8       The construction shall be such as to avoid air or water pockets.  Special care shall be exercised to reduce noise and vibration to the minimum level.

5.9       Steel bolts of suitable finish will be used for diameters above 6mm. Brass bolts or studs used for electrical connections shall not be of less than 6mm dia.  On outdoor equipment, all bolts, nuts & washers in contact with current carrying non‑ferrous parts shall be phosphor bronze:

5.10     All nuts bolts and pins shall be locked except those which are external to the transformer.  If bolts and nuts are so placed as to be inaccessible by means of ordinary spanners, suitable special spanners shall be provided by the supplier.

5.11     Labels shall be provided for all apparatus like relays, switches, fuses, etc.  housed in any cubicle or marshaling kiosks.  These shall be of incorrodible material with matt/satin finish and permanent lettering.   Labels mounted on black surface shall have white letters & danger notices shall have red lettering on a white background.  The labels shall be secured by means of brass screws or rust protected steel screws.

5.12     Surface in contact with oil shall not be galvanized or cadmium plated.

5.13     Before painting, all ungalvanised parts shall be cleaned made free from rust, scale and grease and external rough surfaces smoothened filled with metal deposition.  The interior of the tank and other oil filled chambers shall be cleaned by shot blasting or any other suitable method.

 5.14    All external surfaces shall be given three coats of paints except for nuts, bolts and washers which may be given one coat after erection.  The final coat shall be a glossy oil and weather proof, non‑fading paints of shade 631 of IS:5.

5.15     The interior of mechanism chambers and kiosks shall be given 3 coats of paint, the final coat being of a light coloured anti‑condensation mixture.

5.16     LOCKING OF OUTER RADIAL SPACERS :‑

The outer most radial spacers of the winding shall be locked in position by means of vertical strips so that the same can not fall off/got displaced.

5.17     TIGHTENING OF THE NUTS OF THE COIL CLAMPING BOLTS :‑

The proper & complete tightening of the nuts of the coil clamping bolts must be ensured by the manufacturers.  The tightening of the nuts to the designed value and that the nuts of all the coils clamping bolts are tightened to same extent, should be carried out with torque spanners.

The devices used for locking the nuts of coil clamping bolts must be of such a quality and such care should be taken first in tightening the nuts and next in locking them in position that the arrangement does not work loose due to vibrations caused by short circuits and fluctuating loads etc.

5.18     The noise level shall not be more than 5db above NEMA  standard publication TR‑1.

5.19     The transformers shall be designed to have short circuit rating of two seconds as per ISS‑2026.

6.         INSULATING OIL:-

Sufficient insulating oil of Napthenic type (made from Naphthenic crude) in which paraffinic content should be less than 50% and aromatic content 4 to 12% conforming to BS: 148/IEC:296 class-1 shall be supplied for first filling of each transformer. Particular attention shall be paid to deliver the oil at site free from moisture and of uniform quality through out in non-returnable steels drums. The quantity of oil for first filling of each transformer shall be stated in tender along-with trade mark of the oil to be supplied. Use of inhibitors in oil shall not be resorted to. 10% extra oil of the total quantity of oil shall be supplied along with the transformer.

 

7.         LIMIT OF TEMPERATURE RISE:-

7.1              With the above climatic conditions given in clause-3 each transformer shall be capable of operating continuously on any tap at their normal rating without exceeding the following temperature rises

(i)                  50 deg C in oil by thermometer

(ii)                55 deg C in winding by resistance

(iii)               Winding Gradient i.e the difference between average winding average oil temperature not to exceed 13 deg C.

(iv)              Temperature of hot spot in windings not to exceed 98 deg C when calculated over max annual weighted average temperature of 32 deg C. 

7.2              The limits of temperature rise mentioned above will have to be satisfied by the manufacturer by carrying out the heat run test at the lowest negative tap. This test shall be carried out by feeding 1.1 times the total losses at 75 deg C at highest current tap.

7.3              OVERLOAD CAPACITY & CONTINOUS RATING

The safe overload capacity of the transformer and the duration of overload under maximum temperature conditions without any damage to the winding or harmful effects on the insulation shall be clearly stated in the tender which must be asper IEC-354/IS6600,guide for loading of oil immersed transformer.

8.0              IMPEDANCE

The transformer shall have 10% impedance on 50 MVA base respectively with tolerance as per IS:2026/Part-I(1983). Impedance shall include positive and zero sequence and shall be expressed in terms of the branches of star connected equivalent diagram, all on the same kVA base and range shall be given for each branch of the equivalent circuit in turn. 

9.0       FREQUENCY:-

The transformer shall be suitable for continuous operation with a ±5% frequency variation from a normal of 50 HZ without exceeding the temperature rise as specified in clause-7.1 above.

10.0     FLUX DENSITY, CORE CONSTRUCTION and INSPECTION

 

10.1     The transformer should be so designed that the working flux density should not exceed 1.57 Tesla at normal voltage, frequency.

 

10.2     Tenders with higher flux density than specified limit shall not be considered.

 

10.3     The core shall be built up with thin laminations of high grade. non-ageing, low loss, high permeability cold rolled super grain oriented silicon steel. Known as MOH High B Grade or superior grade CRGO steels of maximum 0.27 mm or low lamination thickness especially suitable for transformer core.

 

10.4(a) (i)Bidder should have in house core cutting facility for proper monitoring & control on quality and also to avoid any possibility of mixing of prime material with defective/second grade material. The purchaser may witness the core-cutting operation. In case the in house core cutting facility for core cutting is not available then the same shall be carried out in the presence of the representative of HVPN.

 

  (ii)Inspection call notice for the purpose should be accompanied with the following  documents as applicable as a proof toward use of Prime core materials        :-

      a)    Invoice of supplier.

      b)    Mills test certificates.

      c)    Packing list.

      d)    Bill of loading.

      e)    Bill of entry certificates by customs.

 

  Core material shall be directly procured either from the manufacturer or through their accredited marketing organisation of repute and not through any agent.

10.4(b) After being sheared, the laminations shall be treated to remove all burrs. They  shall be coated with a baked enamel insulation coating. The insulation shall be inert to the action of hot transformer oil and shall be perfectly adhesive. Paper and varnish insulation shall not be accepted. Particulars of proposed insulation shall be stated in the tender. Laminations shall be checked for burrs during stage inspection.

 

10.5     The core shall be rigidly clamped and/or bolted to ensure adequate mechanical strength and to prevent vibrations during operation. The bolts used in the assembly of the core shall be suitably insulated and the clamping structure shall be constructed that the eddy currents will be minimum.

 

10.6     Construction of the core shall be such that number of steps in the limb and yoke shall be matching and dimensionally identical to minimize the effect of cross fluxing and better mechanical strength.

 

10.7       The core shall be provided with Lugs suitable for lifting the complete core and coil assembly of transformer. The Core & coil shall be fixed in the tank such that its shifting will not occur when the transformer in moved or when a short circuit occurs.

 

10.8       The design of magnetic circuit shall be such as to avoid static discharge development of short circuit paths within itself or to the earthing clamping structure and the production of flux components at right angles to the plane of the lamination which may cause local heating.

 

10.9       Every care shall be exercised in the selection treatment and handling of core steel to ensure that the laminations are flat and that finally assembled core is free from distortions.

 

10.10     The supporting frame work of the core shall be so designed as to avoid the presence of pockets which would prevent complete emptying of the tank through the drain valve or cause trapping of air during filling.

 

10.11     Oil ducts where necessary should be formed across the plane of the lamination and be given a suitable slope to assist oil circulation. The overall design of core and winding should be such that free flow of oil is not obstructed.

 

10.12     The frame work and clamping arrangement shall be earthed by connecting to the tank body through a copper strip. Yoke bolt area should be compensated if bolts are used for fastening of the core.

 

10.13     The insulation of core to bolts and core to clamp plates shall be able to withstand a voltage of 2 KV RMS for one minute.

 

10.14     Core and windings shall be capable of withstanding shocks during transport, installation, service and adequate provision shall be made to prevent movement of core and winding relative to tank during these conditions.

 

10.15     All steel sections used for supporting the core shall be thoroughly sand blasted after cutting drilling and welding.

 

10.16     CRGO used shall be strictly as per approved vendor as below:-

a)        Nippon Steel Corp.Japan

b)       Kawasaki Corp. Ltd.,Japan

 

10.17     The tenderers should indicate the maximum flux density allowable continuously as well as for time intervals of 1 minute and 5 secs. and the limit of flux density at which core material used by them saturates.

 

   10.18     The name of the core material must be mentioned in the tender. The successful tenderer shall be required to furnish magnetization curves of the core material/design calculations and such other data/documents deemed fit by the Purchaser for being satisfied that flux density is as desired.

 

10.19     Purchaser shall inspect the built-up core for verification of flux density for which all facilities shall be provided. The purchaser shall inspect/test the core material for various tests as per relevant IEC/IS to ensure quality. Core may also be inspected during horizontal assembly, built-up assembly.  

 

Notes :

i)          The above flux density has been specified to meet with the over fluxing of the core due to temporary over voltage of the order of 31% for l min, 44%for 5 sec. that may appear abnormal conditions such as those following sudden loss of large loads.

 

ii)         Yoke bolt area and flitch plate areas shall not be counted in the net core area if these are provided for fastening core.

 

iii)             The design of limb and yoke shall be so co-ordinate that there is no cross fluxing at the joints.

 

iv)            The tenderer shall ensure that the CRGO supplier should have BIS certification.

                                                                       

 11.      SUPPRESSION OF HARMONICS:

            The transformer shall be so designed as to suppress the harmonics voltage specially the 3rd & 5th, to eliminate wave form distortion and interference with communication circuits due to high frequency disturbances. Limiting percentage of harmonics at normal voltage and at maximum system voltage shall be stated in the tender.

12.       WINDINGS:-

12.1     The 132kV windings shall have graded insulation whereas all other windings shall be fully insulated and the neutral points shall be insulated as amended in IS:2026.

 

12.2     The transformers shall be capable of operation without danger on any particular tapping at the rated kVA when the voltage may vary by ±10% of the voltage corresponding to the tapping.

 

12.3     The windings and connections, insulation material shall not soften, ooze out, shrink or collapse during service.

 

12.4          No strip conductor wound on edge shall have a width exceeding six times its thickness. The conductors shall be transposed at sufficient intervals to minimize eddy currents and equalize the current and temperature distribution along the windings.

12.5     The windings and connections shall be properly brazed to withstand shocks during transportation or transient conditions during service.

 

12.6     The adequate pre‑shrinkage of the coil assembly using pre‑compressed press board material having low moisture content for the radial spacer blocks shall be ensured by the manufacturers so that there is no displacement of the radial spacer blocks due to frequent short circuits on the transformers.

12.7     All windings after being wound and all fibrous  hygroscopic materials used in the construction of the transformer  shall be dried under vacuum and impregnated with hot oil.

In addition to this the drying process be sufficiently extended for proper stabilization of the coil assembly. More than one cycle of soaking in oil followed by retightening of the coil assembly should be adopted.

12.8     The coil clamping rings wherever used, shall  preferably  be of flat insulated steel laminations.  Auxiliary laminated material except bakelised paper shall not be used.

12.9     The clamping arrangement shall exert equal pressure on all columns of spacers of the transformer windings built of sections or disc‑coils separated by spacers.  In no case, spiral winding will be used either for HV or LV windings.

12.10   The radial spacer blocks must be made of pre‑compressed pressboard material, which will not soften while in contact with oil or fray out into fibers or edges.  The slots should be so dimensioned that the blocks will not come out of the slots.

            Uniform distribution of coil clamping force shall be designed by using an adequately large number of coil clamping bolts and by transferring the clamping force from clamping bolts to the clamping plates through intermediate members which can spread the clamping force over a large area.

12.11   All joints shall be brazed/crimped considering the vibrations due to short circuits and load fluctuations.

13.       CURRENT DENSITY:

The purchaser shall be at liberty to inspect built-up winding for its quality, weight of copper, insulation and overall weight of coil assembly.  The size of conductor used for different windings shall also be checked during stage inspection to check the current density. The transformer shall be so designed that the current density of all the windings and the regulating winding at the lowest tap should not exceed
250 A/cm.Sq
.

14.       TANK CONSTRUCTION:-

14.1.1  The tank shall be fabricated of a suitable grade steel and strong enough to allow the lifting of complete transformer with oil by means of a crane or jacks and transported to site without over‑straining the joints etc.

14.1.2  The main tank body shall be capable of withstanding a vacuum of 100.64 KN/m2  (760mm of Hg.)

14.1.3 The base shall be so designed as to allow the transformer to be moved by skidding without any injury.

14.1.4 All channeled constructions and stiffeners shall be designed to avoid retention of water.

14.1.5  The tank construction shall be free of air pockets, where such pockets cannot be avoided vent pipes of 15 mm internal dia shall be provided to vent gases into the main expansion pipes. In case of short branch pipes, however, minimum diameter may be taken as 6mm.

14.1.6 All joints other than those, which may have to be broken, shall be welded. When required they shall be double welded. All bolted joints to the tank shall be fitted with suitable oil tight gaskets, which shall give satisfactory service under the operating conditions and guaranteed temperature rise conditions. Special attention shall be given to the methods of making hot oil tight joints between the tank and the cover and also, between the cover and the bushings and all other out-lets to ensure that the joints can be remade satisfactorily at site and with ease by semi-skilled labour.

14.1.7  Suitable lifting lugs for lifting the transformer filled with oil shall be provided on the  tank.

14.1.8  Four jacking lugs shall be provided to enable the transformer complete with oil to be lifted or lowered by means of jacks.  The lugs shall be fitted at a minimum height (excluding under base if detachable) of 300mm for transformer upto 10 tonnes weight and of 500mm for transformer above 10 tonnes weights.

14.1.9  The transformer shall be provided with detachable steel flanged wheels of 250mm dia and suitable for moving transformer complete with oil.  These shall be bi-directional and mounted on swivels which may be turned through 90o when the tank is jacked up and capable of being locked in position parallel to and at right angles to the longitudinal axis.  The wheel be suitable for standard gauge track of 1676mm.

14.2     TANK COVER

14.2.1 The tank cover shall be of bolted type and of adequate strength so as not to distort, when lifted. Suitable inspection cover shall be provided with lifting arrangements to give access to bushings, winding connections or testing the earth connections. The weight of each inspection cover shall not exceed 25 Kg.

14.2.2 Pockets shall be provided in the position of Max. oil temperature at CMR for fitting a thermometer and for bolts of oil and winding temperature indicators. The thermometer pockets shall be fitted with a captive screwed cap to prevent ingress of water.

 14.2.3   Suitable No. of jacking bolts shall be provided on tank cover, inspection covers/windows including OLTC.

14.3     CONSERVATOR TANK, OIL GAUGE AND BREATHER

14.3.1  An adequate conservator tank of air cell type complete with sump and drain valves shall be provided in such a position as not to obstruct the electrical connections to the transformer.

14.3.2  If the sump is formed by extending the feed pipe inside the conservator, this extension shall be atleast 25mm.

14.3.3   One end of the conservator shall be bolted type to facilitate cleaning.

14.3.4   The conservator shall be provided with a magnetic oil level gauge.

14.3.5  The oil connections from the transformer tank to the conservator shall be at rising angle of
3 to 9 degrees to the horizontal upto Buchholz relay. The inside diameter of the pipe shall be 80mm. The Buchholz relay will have suitable valves on its both side so as to facilitate its testing at site as well as cut off oil supply to the transformer.

14.3.6   The conservator shall be provided with oil preservation system, which should be suitable either to remove moisture continuously from air entering the air space with which they are connected or may not allow direct contact of atmospheric air with oil during operation, in addition to silicagel‑breather.

14.4        VALVES:

14.4.1     The transformers shall be provided with 2 No. filter valve each of 50 mm size one mounted close to the top of the main tank  & the other close to bottom of the tank oil circulation and one drain valve of 80mm size with plug. The conservator shall have drain plug of 25mm size.

14.4.2     Two robust sampling valves with spouts suitable for taking samples of top, and bottom oil. The top sampling valves shall be brought down by internal pipe connections.  Suitable name plates shall be affixed to the sampling valves. The sampling device shall not be fitted on the filter valve.

14.4.3     Two air release plug of 15mm shall be provided.

14.4.4      Plugs shall be supplied for all valves opening to atmosphere.

14.4.5      All valves shall be of gun metal and comply with the latest edition of IS: 3639.

14.5        PRESSURE RELIEF DEVICES:

               A suitable pressure relief device of 6" diameter shall be provided on the main tank and of 3" diameter shall be provided on OLTC for rapid release of any pressure in transformer, which may endanger the equipment.  The device (s) shall operate at static pressure less than hydraulic test pressure for transformer tank of OLTC chamber. If the device is mounted on tank cover, it shall be fitted with a skirt projecting 25mm inside the tank and of such construction as to avoid gas accumulation. 

               In addition to pressure relief device(s) the provision of explosion vent should also be made and the diaphragm shall be situated above max. oil level or second PRD on the opposite side of the first PRD be provided.

14.6        EARTHING TERMINALS:

14.6.1    Two earthing pads suitable for connecting 50x8mm mild steel flat shall be provided at positions close to the two diagonally opposite bottom corners of tank. These grounding terminals shall be suitable for bolted connection.  Two earthing terminals shall also be provided each on marshalling box and any other equipment mounted separately.

14.7        JOINTS AND GASKETS: -

14.7.1     All gaskets used for making oil tight joints shall be of granulated cork bonded with synthetic rubber.  Metal tops shall be provided for preventing over compression wherever compressible gaskets are provided.

14.8        RATING AND DIAGRAM PLATES:

14.8.1     Each transformer shall carry a diagram plate showing internal connections, voltage vector relationship of different windings, plan view of the transformer showing physical relationship of the terminals and no load voltage and corresponding current for each tap.

14.8.2       Each transformer shall be provided with a rating plate data as specified in IS: 2026.

14.8.3       I.R. values alongwith oil temperature at the time of testing at manufacturer's works shall be indicated on rating plate or separate plate, to be provided on transformer.

14.9        THERMOSYPHON FILTER ARRANGEMENT

 

Thermosyphon filter arrangement shall be provided on the transformer for preserving the quality of Transformer Oil. The filter assembly shall be mounted on the Transformer as well as ground supported and connected with pipes and shut off valves. Suitable instructions required to be followed for commissioning, dismantlement & maintenance of the filter arrangement, re-generation and storage of the adsorbent etc. must be included in the instruction manual. A detailed drawing showing internal arrangement, shall also be required to be submitted. Suitable capacity pump (alongwith motor) shall also be provided to boost circulation of oil. The pump and motor should not be in main pipe line. It should be in bypass pipe line having suitable valve to isolate from main pipe line. The main pipe line should have two shut off valves at the bottom.

 

   NOTE: -       The pump and motor should be weather proof(Flow well Type).

 

              The oil & sorbent capacity required in the Thermosyphon Filter is as under: -

           

              (i)       Quantity of oil                         2.0% of total oil by weight.

             (ii)       Quantity of adsorbent            1.25% of total oil by weight.

15.       COOLING PLANT:-

15.1       Detachable radiators shall be fitted on the main tank with machined flanged outlet and inlet.  Each radiator shall be provided with 19mm drain plug at Bottom and 19mm air release plug at the top.  Valves shall be provided on the tank at each point of connection to radiators.

15.2       In case separate cooler banks are used, they shall be suitable for mounting on a flat concrete base.  These shall be provided with a valve (25 mm) at each point of connection to the transformer tank, removable blanking plates to blank off main oil connections to each cooler.  25 mm drain valve.  Thermometer pockets with captive screwed cap at inlet and outlet of each separate cooler, filter valve at top and bottom and air release plug of 15mm.

15.3     The motor blowers shall be direct driven suitable for continuous out door operation and complete with necessary air dusting.  These shall be mounted independently from the radiator and in the case, these are radiator mounting type, use shall be made of some anti‑vibration means.  Care shall be taken that the blower unit is capable of being removed without disturbing the radiator structure.  The blades shall be suitably painted and shall not be of hollow sections.  Suitably painted wire mesh guards with mesh not greater than 25mm shall be provided to prevent accidental contact with the blades.

15.4     MOTORS:-

15.4.1 The motor shall be squirrel cage totally enclosed weather proof type suitable for direct starting and for continuous running from 415‑240 volts, three phase/single phase 50 C/S supply.  The motors shall comply with IS as applicable for continuous rated machine.

15.4.2 All motors shall be capable of continuous operation at frequency 50Hz with variation of ±5 % and 415/240 V AC ± 10 % variation of the normal voltage without injurious over heating.

15.4.3 All motors shall have ball or roller bearing with hexagonal nipples for greasing. In case of vertical spindle, motor shall have bearing capable of withstanding thrust, due to weight of the moving parts.

15.4.4 Varnished cambric or glass insulator shall be used for connections from stator winding to the terminal suitable for external wiring.  The motor terminals shall be of stud type and totally enclosed.

15.5     COOLER CONTROL:-

15.5.1 Each motor or group of motors shall be provided with a 3 pole electrically operated contactor with control gear for motor operation by hand and automatically through winding temperature indicator. Provision shall be made for over load protection but no volt release shall not be provided.

15.5.2 All connection shall be so arranged as to allow either individual or collective operation of the motors, Alarm indication (audio and visual) for failure of fans and to indicate failure of power supply shall be provided.

15.5.3 The control equipment shall be installed in the marshaling box as specified in Cl.20 in readily accessible position.

15.5.4 The alarm indication for failure of power supply and failure of individual fans be provided through independent non trip alarm scheme conforming to the following:‑

i)          The closing of an initiating contact shall actuate a buzzer and will be accompanied by a flag indication on the concerned auxiliary relay.

ii)         The closing of an initiating contact shall glow a lamp, which will not reset until the fault has cleared.

iii)         It shall be possible to silence the buzzer by pressing 'Accept' push button.  If after canceling the alarm but before resetting the visual signal, the same fault persists the buzzer shall be suppressed.

iv)        If after canceling the alarm but before resetting the visual signal, some other fault takes place, the alarm accompanied by flag indication on appropriate auxiliary relay shall taken place.

v)         If after canceling the alarm and after resetting the visual signal, the same fault appears or some other fault take place, the alarm, flag indication and non‑trip lamp indication shall reappear as usual.

vi)        The non‑trip alarm acceptance shall be by means of push button and resetting of visual signal may also preferably be done through a push button.

vii)        Means shall be provided for test checking the lamp and alarm circuit at frequent intervals.

viii)              The equipment shall be suitable for 220 Volts DC operation.

         Static facia aunnuciator conforming to the foregoing requirements of non trip alarm scheme too would be acceptable.

16.         VOLTAGE CONTROL (ON LOAD TYPE):-

16.1        The transformer shall be provided with voltage control equipment of the tap  changing type for varying its effective transformation ratio while the T/Fs are on load and without producing phase displacement.

16.2        Equipment for 'local' and 'remote' electrical and 'local' manual operation shall be provided and shall comply with the following conditions.  Local/ remote switch may be housed in remote control panel or in tap changer drive mechanism.

16.2.1     It shall not be possible to operate the electric drive when the manual operating gear is in use.

16.2.2     It shall not be possible for any two electric controls to be in operation at the same time.

16.2.3     The equipment suitable for supervisory control and indication on a multi way switch, make‑before break, having one fixed contact for each tap position, shall be provided and wired to the tap changer drive gear. This switch shall be provided in addition to any, which may be required for remote tap change position indication purpose. Supervisory indication shall also be provided in the form of contacts to close on. "Tap change incomplete" condition. All other components of the supervisory gear if required be specified separately.

16.2.4     Operation from the local or remote control switch shall cause one tap movement only. The control switch shall be returned to the 'neutral' position ­between successive operations.

16.2.5     All Electrical control switch on the local operation gear shall be clearly labeled in a suitable manner to indicate the direction of tap changing.

16.3             The equipment shall be so arranged as to ensure that when a tap change   has commenced, it shall be completed independent of the operation of the control relays or switches.  In case of failure of the auxiliary supply while tap change is in progress or any other contingency such as stuck tap changer, adequate means shall be provided to safe guard the transformers and its auxiliary equipment.

16.4        Suitable apparatus shall be provided for each transformer to give indications as follows: -

16.4.1     To give indication, mechanically at the transformer and electrically at the remote control cubicle of the position of tap in use.

16.4.2     To give an indication at the remote control cubicle that a tap change is in-progress, by means of an illuminated lamp.

16.5        For remote control, the switches, tap position indicator, etc. shall be supplied duly mounted on remote control cubicle.

16.6        All relays and operating devices shall be operated correctly at any voltage between the limits specified in the relevant ISS.

16.7        The tap changing mechanism and mechanism shall be mounted in the oil tank or compartment mounted in an accessible position on the transformer.

16.8        Any non oil filled enclosed compartment shall be adequately ventilated, Thermostatically controlled heaters shall be provided in the driving mechanism chamber and in the marshaling box. All contactor & auxiliary  relay coils or other parts shall be suitably protected against corrosion or deterioration due to condensation, fungi etc.

16.9        The tap changer contacts which are not used for making or breaking current like separate selector switch contacts can be located inside main transformer tank where tap changer construction permits such an arrangement. The oil in case of on load tap changer having separate compartment for selector contacts shall be maintained under conservator head by means of pipe connection from the highest point of the chamber to the conservator.  Such connection shall be controlled by suitable valve and shall be arranged so that any gas leaving the chamber will pass into the gas and oil actuated relay. A separate buchholz relay may be provided for this compartment.

16.10      It shall not be possible for the oil in these compartments of the tap change equipment which contain contacts used for making or breaking current, to mix with the oil in the compartments containing contacts and not used for making or breaking current.

16.11      Any 'DROP DOWN' tanks associated with the tap changing apparatus shall be fitted with guide rods to control the movement during lifting or lowering operations.  The guide rods shall be so designed as to take support of the associated tank when in the fully lowered position with oil.  Lifting gear fitted to 'Drop Down' tanks shall include suitable device to prevent run‑away during lifting and lowering operations. They shall be provided with adequate breathing arrangement.  The tap changer shall be mounted in such a way that the cover of the transformer can be lifted without removing connections between windings and tap changer.

16.12      Each compartment in which the oil is not maintained under conservator head shall be provided with a suitable direct reading oil gauge.

16.13      The alternating supply for electrical operation of the control and indicating gear shall be standard 415 Volts, three‑phase, 3 wire, 50 Hz. alongwith 240 Volts single phase, 2 wire 50 Hz, subject to a variation of ±5 percent so that the equipment offered can withstand variation in AC

16.14      Limit switches shall be provided to prevent over-running of the mechanism and except where modified in clause 18.15 shall be directly connected in the circuit of the operating motor.  In addition a mechanical stopper or other approved device shall be provided to prevent over‑running of the mechanism under any condition.

16.15      Limit switches may be connected in the control circuit of the operating motor provided that a mechanical declutching mechanism is incorporated.

16.16      Thermal devices or other means like motor circuit breakers with shunt trip coil shall be provided to protect the motor and control circuits.  All relays, switches fuses, etc. shall be mounted in the marshaling box or driving gear housing. These shall be clearly marked for purpose of identification. They shall withstand the vibration associated with tap changer gear operation.

16.17      The control circuits shall operate at 110V single phase to be supplied from a transformer having a ratio of 415 or 240/55‑0‑55 V with the center point earthed through a removable link mounted in tap changer drive.

16.18      The whole of the apparatus shall be of robust design and capable of giving satisfactory service under conditions to be met in service including frequent operation.

16.19      A five‑digit counter shall be fitted to the tap changing mechanism to indicate the number of operations completed by the equipment.

16.20      A permanently legible lubrication chart shall be fitted within the driving mechanism chamber, where applicable.

16.21      The indigenous make OLTC suitable for 132 KV voltage class insulation (graded) but the voltage class insulation should not be less than 66 KV and current rating as 300 Amp. The OLTC should be type tested from CPRI or other Govt. test house or from reputed Lab. Abroad to the extent the facilities of type test are available with CPRI.

 

17.          PARALLEL OPERATION :-

17. 1       In addition to individual control of tap changer, provision shall be made to enable parallel operation of the tap changer when one unit is running in parallel with another similar unit of same rating.

17.2        Suitable selector switch and controls shall be provided so that any transformer of the group can at a time be selected as master, follower or independent. Arrangement shall be made that only one of the transformers can be selected as master at a time.

17.3        An out of step device shall be provided for each transformer indicating out of step condition by an indicating lamp and buzzer.  It shall be arranged to prevent further tap changing when transformers in a group operating in parallel control are one tap out of step.

 

18.          BUSHING INSULATORS AND TERMINALS:

18.1        Transformer shall be fitted with bushing insulators as follows: -

            HV bushing: 145 kV class, condenser bushing of 800 Amp. rating with arcing horns.

                                   L.V. Bushing: 36 kV class, oil communicating type porcelain bushing of 1000 Amp. rating but with suitable arcing horns.

                                   L.V.-N Bushing: 36 kV class, oil communicating type porcelain bushing of 1000 Amp. rating but without arcing horns.

                                   H.V-N Bushing: 36 kV class, oil communicating type porcelain bushing of 630 Amp. rating but without arcing horns.

·         The characteristics of the bushings shall be in accordance with IS: 2099 and IS: 3347.

·         The bushing insulators except for neutral bushing shall be provided with adjustable arcing horns and the bidder shall furnish calibration gap to   decide actual gap setting.

·         A continuous flexible pull through lead suitably sweated to the end of winding copper shall be connected to the connector in the helmet of the 220/132 kV Bushing. The bushings may be filled with oil, which may not be in communication with the oil in transformer.

·         All porcelain shall be free from defects and thoroughly vitrified with a smooth, hard and uniform brown glaze.  It should be capable of satisfactory use under the climatic conditions as specified in clause-3.0.

·         In case of paper insulation care shall be taken to prevent ingress of moisture and a final coat of non‑hygroscopic varnish shall be given to them.

·         All clamps and fittings made of malleable iron or steel shall be galvanized as per IS: 2629.  The bushings flanges shall not be of re‑entrant shape which may trap air.

·         Bi‑metallic terminal connectors shall be supplied suitable for single 0.4 Sq. inch ACSR Zebra conductor for HV, LVN & HVN and twin ACSR Zebra conductor for LV side . The take off for H.V. & L.V. connectors will be Vertical and for Neutral it should be suitable for horizontal take off.

·         The connectors shall have six number bolts provided with check nuts & washers. The connectors shall have rating corresponding to those of equipment or higher and shall be designed most liberally with a higher factor of safety to comply in all respects with temperatures rise, resistance, tensile strength short‑circuit withstand capability tests as specified in IS: 5561‑1970 or amendment thereof (Latest edition). Aluminum alloy used in the manufacture of Bi-metallic connectors shall conform to designation Grade 4600 of IS: 617‑1975. The steel bolts, nuts washers and check nuts shall be hot dip galvanized marked with ISI certification mark or of GKWmake.

 

19.          TEMPERATURE INDICATING DEVICES:

19.1        All transformers shall be provided with a dial type thermometer for indicating oil temperature. The indicator shall be fitted with a pointer to register maximum temp recorded and adjustable set of mercury contact for alarm and trip.

19.2        In addition, all the transformers shall be provided with a dial type Hot Spot winding temperature indicator in HV & LV winding. The indicator shall have a pointer to register maximum temperature reached and four sets of adjustable mercury contacts for alarm, trip, automatic control of fans & remote indication. The static remote repeater (for winding temperature indicator) suitable for flush mounting shall be installed on remote tap charge control cubicle.

19.3        The temperature indicators shall be housed in marshaling box.

19.4        The alarm (mercury) contact of WTI & OTI shall be adjustable between 50oC to 100oC where as their trip (mercury) contacts shall be adjustable  between 60oC and 120oC. The temperature difference between opening & closing of these mercury contacts shall not be more than 10oC.

19.5        The mercury contacts used for controlling cooling plant motors shall be adjustable to close between 50oC and 100oC. The temperature differential between opening & closing of this mercury contract shall be between 10oC  to 15oC.

19.6        All contacts should be accessible on removal of the cover adjustable to scale.  It shall also be possible to move the pointers by hand for checking the operation of contacts and associated equipment.

19.7        In addition each transformer shall be provided with a dial type thermometer for indicating the ambient temperature.

20.          GAS AND OIL ACTUATED RELAYS: -

20.1        The transformer shall be provided with a gas and oil actuated relay fitted with alarm and trip contacts for main tank & oil surge relay  for its OLTC as per IS:3637.

20.2        Each such relay shall be provided with a test cock to take a flexible connection for checking relay operation

20.3        A machined surface shall be provided on top of relay for checking mounting angles in the pipe cross level of relay and its setting.

20.4             The pipe work shall be such as to allow any gas formed in the tank to pass through the relay.  The oil circuit through the relay shall not form a parallel delivery path with any circulating oil pipe, nor shall it be tied into or connected through the pressure relief vent.

20.5             Adequate clearance between oil pipe work and live metal parts shall be provided.

21.          MARSHALING BOX:

 21.1         A sheet steel (of 10 SWG size) vermin proof well ventilated and weather proof marshaling box of suitable construction shall be provided for the transformer auxiliary apparatus. The box shall have domed or sloping roofs.  Ventilation louvers, suitably padded with felt, shall also be provided.  It shall be painted as per Cl.5.14.

21.2        The marshaling box shall accommodate temperature indicators.  Local electrical control of tap changer (if same cannot be housed in motor drive housing.), Control & protection equipment for cooling plant, terminal boards and gland plates for cable etc.  The equipment shall be mounted on panels and panels wiring shall be done at the back for interconnections.

21.3        The temperature indicators shall be mounted at about 1600mm from ground level.

21.4        A metal clad heater with thermostat, controlled by a waterproof rotary switch on the outside of the box, shall be provided.

 

21.5        The incoming cables shall enter from the bottom with gland plate not less than 450mm from the base of the box. Care shall be taken to avoid ingress of water from the cable trench.

22.          CONTROL CONNECTIONS, INSTRUMENTS WIRING, TERMINAL BOARD AND FUSES: -

22.1        All cables and wiring shall be suitable for use under the conditions as specified in Section -I. Any wiring liable to come in contact with oil shall be of oil resisting insulation.  The bare ends of stranded wire shall be sweated together to prevent oil from creeping along the wire.

22.2        The instrument and panel wiring shall be run in PVC or non rusting metal cleats of limited compression type.

22.3        The box wiring shall be as per relevant ISS.  All wiring shall be of stranded copper of 660V grade and size not less than 4 Sq. mm. for CT leads and not less than 2.5 Sq. mm for other connections.  The panel wires and multi core cable shall bear ferrules of white insulation material with indelible marking in black and as per relevant ISS.  Same ferrule number shall not be used on wires in different circuits. Double ferrule may be provided where a change in number is required.

22.4        Stranded wires shall be terminated with tinned Ross Courtney terminals, washers or crimped tubular lugs. Separate washers shall be used for each wire. Wire shall not be jointed/tied between terminal points.

22.5        Where apparatus is mounted on panels all metal cases shall be separately earthed by copper wire or strip not less than 2.5 sq. mm.  The screens of screened pairs of multi core cables shall be earthed at one end of the cable only.

22.6        All terminal boards shall be of stud-type & mounted obliquely towards the rear door and these boards shall be spaced not less than 100mm apart.  Suitable insulation barriers shall be provided between adjacent connections.  No live metal shall be exposed at the back of terminal boards.

22.7        All fuses shall be of cartridge type and fuses and links shall be properly labeled.

23.          EQUALIZATION FORMULA:

               The losses at principal tap of each transformer shall be stated in the tender ONAF rating at full load at 750C.

               For the purpose of arriving at comparable prices, the iron, copper and auxiliary losses shall be capitalised as per capitalization formula given below:

               =3,86,700( Wi + 0.45 Wc + 0.45 Wp)

               Where        

                                   Wi                               =          Iron (No load) Losses

                                   Wc                             =          Copper (Load Losses)

                                   Wp                             =          Auxiliary Losses

              

               The maximum sealing of component and weightage average losses shall be as per clause 24.0 and no positive tolerance shall be allowed on these values

In case losses of the T/F are found to be higher then the specified values at any stage within three years from the date of commissioning the capaitalized value of excess losses, as compare to the specified value shall be recovered as per following capitalization formula:-

Amount recoverable (Rs.)= 3,86,700 (Wi + 0.45 Wc + 0.45Wp).


 

24.          Losses:-

The losses of each transformer shall be stated in the tender for OFAF at principal tap rating (at full load at 75 deg. C) which shall be less than:-

 

Sr. No.

Type of Losses

40/50 MVA, 132/33 KV T/F

1

No Load Losses

30 KW (Max)

2

Load Losses

200 KW (Max)

3

Auxiliary Losses

4.0KW (Max.)

4

overall average wt. losses (based on capitalisation formula of Wi+0.45 (Wp+Wc)

110KW (Max.)

 

 

24.1        Noise level                          :           80 dB

 

  Transformer offers shall be rejected if audible sound level is higher than max.80  dB.

 

25.          TESTS:

25.1        ROUTINE TESTS:   

               All routine test shall be carried out on each transformer as per IS-2026/ IEC-76. In the presence of purchaser’s representative.

 

25.2        TYPE TEST

               Following type test shall be carried out on one transformer as per ISS 2026 in the presence of purchasers representative.

               (i) Temperature rise test   (along with DGA).

               (ii) Impulse   voltage withstand test as per clause 13 of ISS-2026 /1981 Part-III on one limb.

 

25.3        In addition, the following tests shall be carried out on the Transformer Tank:

25.3.1     OIL LEAKAGE TEST:

               All tanks and oil filled compartments shall be tested for oil tightness by being completely filled with  oil of viscosity not greater than that of insulating oil to IS: 335 at ambient temperature and  subjected to  a pressure equal to normal pressure plus 35KN/M2  (5 lbs sq. inch) measured at the base of the tank. This pressure shall be maintained for a period not less than 12 hours, during which period no leakage shall occur.

25.3.2     Following tests shall be carried out on each transformer as reference test

i.       Measurement of tan delta and capacitor of T/F Winding and bushings at 5kV
& 10 kV.

ii.       Magnetic balance test.

iii.      Magnetising current at low voltage

iv.      Measurement of percentage impedance at all taps at low voltage.


25.3.3     TRANSFORMER OIL:

               Sufficient quantity (along with 10% extra) of insulating oil of napthenic type (as per Clause-6 of specification) conforming to BS:148/IEC-296 Class-1 shall be put up for inspection, at least 3 weeks before putting up the transformer for testing/inspection, at sub-supplier works as per IS:335/BS/IEC. One sample of the oil shall also be got tested from CPRI or any other Govt. approved testing house. The inspected oil shall be dispatched to site as per dispatch instructions of purchaser.

25.3.4     SHORT CIRCUIT TEST

Short circuit test in accordance with clause 16 of ISS-2026  or latest edition shall be got conducted on one of the units at any test Agencies where facilities exist in the presence of Purchaser's  representative  .However, in case of those manufacturers who have already got short circuit test in accordance with Cl. 16 of ISS-2026 or latest edition conducted during the last 5 years on same design and capacity of the Transformer, fresh short circuit test is not required to be conducted. The bidder in such a case shall submit the copy of type test report along with the bid. If this test is not conducted by the firm earlier, then charges for this test shall be borne by the bidder.

The warranty in case of Power Transformer shall be 18 months from the date of commissioning or 24 months from the date of receipt whichever is earlier. All other stipulations of Warranty Clause as per Schedule-D of purchase regulation shall remain same.

25.4       The purchaser reserves the right to have any other, reasonable test carried out at his   expense either before shipment or at site to ensure that the transformer complies with the requirement of this specification.

25.5        STAGE INSPECTION:

               Stage inspection of built up core (in horizontal/vertical position), windings, tank and radiators shall be carried-out as detailed below:-      

               a.      CORE:

i)            Measurement of flux Density.

ii)          No Load Loss Measurement by providing dummy oils.

iii)         Tests of CRGO sample taken from the core shall be carried-out for Carlite test (Resistance Measurement), Watt Loss Test, Lamination Thickness & Aging Tests.

iv)        Physical inspection for quality of workmanship.

v)          Slitting/Cutting of core.

b.      WINDINGS:

i.       Measurement of cross-sectional area for current density.

ii.       Measurement of weight of bare copper/ cover by resistance methods.

iii.    The purity test of copper shall be got conducted on sample of copper for assessing its quality, from two independent NABL accredited laboratories. 

c.      TANK:

                  i)   Vacuum Test:

                  One transformer tank out of the lot shall be subjected to vacuum pressure of 100.64 kN (760 mm of hg). The tanks to be designed for full vacuum shall be tested at an internal pressure of 3.33 KN/M2 (25mm of Hg.) for one hour.

                  The permanent deflection of flat plates after the vacuum has been released shall not exceed the values given below without affecting the performance of the Transformer.


‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑----------------------------‑‑‑‑‑‑‑‑‑‑‑‑‑‑----------------------

Horizontal length of flat plate (mm).        Permanent deflection (mm).

---------------‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑-------------------‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑-------------------

                  Upto & including 750                                                   5.0

                  751‑1250                                                                    6.5

                  1251‑1750                                                                   8.0

                  1751‑2000                                                                   9.5

                  2001‑2250                                                                11.0

                  2251‑2500                                                                12.5

                  2501‑3000                                                                16.0

                  above 3000                                                               19.0

-------------‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑‑-------------------‑‑‑‑‑‑‑‑‑‑‑‑‑-----------------------

                  ii)  PRESSURE TEST:

                  One transformer out of the lot shall be subject to the pressure corresponding to twice the normal head of oil or normal pressure plus 35KN/M2 (which ever is lower) measured at the base of  the tank and maintained for one hour.  The permanent deflection of flat plates after removal of excess pressure shall not exceed the figures specified as above.

            d.        RADIATORS:

                  Radiator shall be routine and type tested at sub suppliers' work as per relevant standard. Test reports are required to be supplied at the time of final inspection.

NOTE:    a.       The insulation resistance values of the transformer windings will be recorded at the time of carrying out routine tests, for 20 seconds, one minute, two minutes with the help of 5000V motorized meggar. (Preferably EVERSHED/ AVO & VIGNOLE MAKE). The polarisation index values (ratio of 120/20 sec. value) will be accordingly calculated and recorded in the test certificates and it should not be less than 1.5.

b.      Dissolved gas analysis test shall be got carried-out before and after heat run test at CPRI.

c.      Capacitance and Tan Delta values for each transformer and condenser bushings will be taken and recorded in the test certificates at 5 kV & 10 kV. Insulation resistance value of condenser bushings shall also be recorded.

d.      Lightening impulse test with the chopped wave applications as per clause 13 of IS: 2026/ 1981 (Part-III) amended upto date. This test will be carried out on one of the limbs of HV and LV winding with positive polarity.

e.      The tender should clearly indicate the testing facilities available with them and tests which are to be arranged outside.

                  Supplier shall submit in house test certificates at least 15 days in advance for final testing of T/F. For testing T/F, all measuring instruments shall be of highest efficiency and best quality. These shall be got calibrated from NPL/ Govt. Agency and be got sealed by calibrating agency.  HVPN reserves the right to calibrate the instruments in the manner it desires.

                  Losses shall be measured with 3-wattmeter method only. Resistance shall be taken with Double-Kelvin Bridge. Losses can be measured directly from CTs and PTs and not through the panel. Ratio of the measuring instrument shall be such that the multiplying factor is the minimum.

                  All tests shall be carried out in the presence of the Purchaser before dispatching the material. Test certificates in quadruplicate will be submitted to the Purchaser for approval. No material shall be despatched without prior inspection and approval of test certificates unless otherwise agreed to. Type and routine test certificates of all bought out items from recognised testing agency shall be submitted for approval before commencing supplies. OLTC scheme including the master follower functioning shall also be checked. Only fully assembled transformer including mounting of radiators shall be put-up for inspection.

 26.            DRAWINGS:

26.1           The following drawings shall be supplied as part of the tender.

26.1.1        Outline dimensional drawing of transformer and accessories.

26.1.2.1     Bushing and terminal connectors drawing.

26.2          The successful bidder shall submit final version of drawings complete in all respects as detailed in the following sub-clauses, in quadruplicate, within four weeks of placement of order for purchaser’s approval.  The purchaser shall communicate his comments/approval on the drawings to the supplier within four weeks of their receipt. The manufacturer shall, if necessary, modify the drawings and resubmit the same for purchaser’s approval within two weeks of receipt of comments. Such duly revised drawings will be approved by the purchaser within two weeks of the receipt.

 

After receipt of purchaser’s approval to drawings, the manufacturer will submit a set of re-producible of all the approved drawings and will also supply five sets of all approved drawings and five sets of manual of instructions per transformer to sub-station Design Directorate, HVPNL, Panchkula.  

 

ONE SET OF ALL THE APPROVED DRAWINGS AND MANUAL OF INSTUCTIONS WILL BE SUPPLIED ALONGWITH EACH TRANSFRMER WITHOUT WHICH THE SUPPLY WILL NOT BE CONSIDERED AS COMPLETE SUPPLY.

26.2.1    Outline general arrangement drawings showing plan, front elevation & side elevation with all fittings and accessories etc. The following information must be specifically included on the drawings.

                 a.    Make of transformer oil.

                 b.    Electrical clearances, minimum as well as actual.

c.    No. of radiator headers, number of radiator element in each header.

d.     Small sketch showing un-tanking details.

e.     Thickness of transformer tank bottom, side & top plates.

   f.      Type, shade, shade No. and thickness of transformer paint.

   g.     Roller, rail gauge sketch.

   h.     Weight of oil, bare copper weight windings, core, un-tanking mass, transportation mass and dimensions etc.

 

26.2.2        Detailed of bushings showing plan, elevation, terminal details, mounting details make and type number incorporating electrical characteristics, description of various parts, total creepage/ & protected creepage distance, weight of oil, total weight of bushing , dimensions, short time current rating etc.

26.2.3        Drawing showing HV & LV windings with arrangement of insulation and terminal connections.

26.2.4        Schematic control and wiring diagram for auxiliary equipment like OLTC control gear, cooler control gear, Marshaling Kiosk.  Detailed write‑up for schematic shall also be supplied

26.2.5        Combined Rating & Diagram Plate.

26.2.6        Valve schedule plate.

26.2.7       Core assembly drawing with flux density calculations.

26.2.8       Interconnection diagram between OLTC panel, Drive mechanism and   marshalling kiosk.

26.2.9         Detailed calculations showing short circuit with stand capability due to radial and axial forces during short circuit. Also calculation for thermal withstand capability during short circuit.

26.2.10Cable arrangement on the transformers.

26.2.11         Drawing showing connection of HV, LV lead with the respective bushing and  their place of storage during transportation.


 

SR. NO.

DESCRIPTION

PARTICULARS

 

 

Required

Offered

1

Manufacturers Name

 

 

 

 

 

 

2

Rating (MVA)

 

 

 

 

 

 

3

Voltage Ratio (KV)

 

 

 

 

 

 

4

Winding Connection

 

 

 

 

 

 

5

Vector Group

 

 

 

 

 

 

6

Number of Phase

 

 

 

 

 

 

7

Frequency (Hz)

 

 

 

 

 

 

8

Type of cooling

 

 

 

 

 

 

9

Rating available at different cooling %

 

 

 

 

 

 

10

Impedance data

 

 

 

 

 

 

a

Guaranteed positive sequence impedance between HV-LV at 75 deg.C with 100% rating at

 

 

 

i. Principal Tap

 

 

 

ii. Maximum Tap

 

 

 

iii. Minimum Tap

 

 

 

 

 

 

b

Zero sequence impedance at principal tap

 

 

 

 

 

 

11

Guaranteed losses at 100% rated voltage (excluding cooler loss) at 75 deg.C between HV and LV

 

 

 

 

 

 

a

Iron loss (KW) (max)

 

 

 

 

 

 

b

Copper loss (KW) (max)

 

 

 

 

 

 

c

Guaranteed cooler losses at

 

 

 

 

 

 

(i)

100% load (max) (KW)

 

 

 

 

 

 

12

Overall average weightage loss (KW) (Max.)

 

 

 

 

 

 

13

Cooling equipment details

 

 

 

 

 

 


 

a

Number of coolers and rating as per % of transformer cooling equipment

 

 

 

 

 

 

b

Mounting

 

 

 

 

 

 

c

Fan motor data

 

 

 

 

 

 

i

Number per cooler and rating as % of cooler requirement (also indicate no.of spare fans)

 

 

 

 

 

 

ii

Type

 

 

 

 

 

 

iii

Rating (KW)

 

 

 

 

 

 

iv

Locked rotor current (Amps)

 

 

 

 

 

 

v

Temp. range over which cooler control is adjustable (deg.c to deg.C)

 

 

 

 

 

 

d

Oil pump motor data

 

 

 

 

 

 

i

Number per cooler and rating as % of cooler requirement (also indicate no.of spare pump)

 

 

 

 

 

 

ii

Type

 

 

 

 

 

 

iii

Rating (KW)

 

 

 

 

 

 

iv

Locked rotor current (Amps)

 

 

 

 

 

 

v

Temp. range over which cooler control is adjustable (deg.c to deg.C)

 

 

 

 

 

 

e

Type of oil pump and motor (whether oil submerged type)

 

 

 

 

 

 

f

Radiator details

 

 

 

 

 

 

i

Overall dimensions lxbxh (mm)

 

 

 

 

 

 

ii

Total weight with oil (Kg)

 

 

 

 

 

 

iii

Total weight without oil (Kg)

 

 

 

 

 

 

iv

Thickness of Radiator tube (mm)

 

 

 

 

 

 

v

Type of mounting

 

 

 

 

 

 


 

14

Thermal Data

 

 

 

 

 

 

a

Temperature rise in top oil over an ambient of 50 deg.C

 

 

 

 

 

 

b

Temp rise in winding by resistance measurement method over an ambient of 50 deg.C

 

 

 

 

 

 

c

Thermal time constant (Hours)

 

 

 

 

 

 

15

Withstand time for three phases short circuit at terminals (secs)

 

 

 

 

 

 

16

Over excitation withstand time (sec)

 

 

 

 

 

 

i

1.25

 

 

 

 

 

 

ii

1.4

 

 

 

 

 

 

iii

1.5

 

 

 

 

 

 

17

Bushings

 

 

 

 

 

 

a

High voltage

 

 

 

 

 

 

i)

Manufacturer

 

 

 

 

 

 

ii)

Type

 

 

 

 

 

 

iii)

Total creepage distance (mm)

 

 

 

 

 

 

iv)

Protected creepage distance (mm)

 

 

 

 

 

 

v)

Mounting

 

 

 

 

 

 

vi)

Rated current (Amps)

 

 

 

 

 

 

b

Low voltage

 

 

 

 

 

 

i)

Manufacturer

 

 

 

 

 

 

ii)

Type

 

 

 

 

 

 

iii)

Mounting

 

 

 

 

 

 

iv)

Total creepage distance (mm)

 

 

 

 

 

 


 

V

Protected creepage distance (mm)

 

 

 

 

 

 

vi)

Rated current (Amps)

 

 

 

 

 

 

C

Neutral Bushing

 

 

 

 

 

 

i)

Manufacturer

 

 

 

 

 

 

ii)

Type

 

 

 

 

 

 

iii)

Mounting

 

 

 

 

 

 

iv)

Total creepage distance (mm)

 

 

 

 

 

 

v)

Protected creepage distance (mm)

 

 

 

 

 

 

vi)

Rated current (Amps)

 

 

 

 

 

 

18

Is Vacuum filling required, if so state absolute pressure (mm of Hg)

 

 

 

 

 

 

19

Total quantity of oil (ltrs)

 

 

 

 

 

 

20

Tap changing equipment

 

 

 

 

 

 

a)

Voltage class and current

 

 

 

 

 

 

b)

Number of steps

 

 

 

 

 

 

c)

Range

 

 

 

 

 

 

d)

Step voltage

 

 

 

 

 

 

e)

Type

 

 

 

 

 

 

f)

Rated voltage of drive motor (volts)

 

 

 

 

 

 

g)

No.of revolutions to complete one step

 

 

 

 

 

 

h)

Time to complete one step on manual / auto operation (sec)

 

 

 

 

 

 

i)

Power required (kw)

 

 

 

 

 

 

21

Insulation level

 

 

 

 

 

 


 

a)

HV windings

 

 

 

 

 

 

i)

Lightning impulse withstand voltage

 

 

 

 

 

 

ii)

Power frequency withstand voltage (kv rms)

 

 

 

 

 

 

b)

LV Winding

 

 

 

 

 

 

i)

Lightning impulse withstand voltage

 

 

 

 

 

 

ii)

Power frequency withstand voltage (kv rms)

 

 

 

 

 

 

c)

HV Bushing

 

 

 

 

 

 

i)

Lightning impulse withstand voltage

 

 

 

 

 

 

ii)

Power frequency withstand voltage (kv rms)

 

 

 

 

 

 

d)

LV Bushing

 

 

 

 

 

 

i)

Lightning impulse withstand voltage

 

 

 

 

 

 

ii)

Power frequency withstand voltage (kv rms)

 

 

 

 

 

 

e)

Neutral Bushing

 

 

 

 

 

 

i)

Lightning impulse withstand voltage

 

 

 

 

 

 

ii)

Power frequency withstand voltage (kv rms)

 

 

 

 

 

 

22

Approximate dimensions

 

 

 

 

 

 

a)

Tank (lxbxh) mm

 

 

 

 

 

 

b)

Overall dimensions with (mm) coolers lxbxh

 

 

 

 

 

 

c)

Shipping dimensions (mm) (lxbxh)

 

 

 

 

 

 

d)

Height for untanking (mm)

 

 

 

 

 

 

e)

Dimensions of largest (mm) package (lxbxh)

 

 

 

 

 

 

23

Weights of transformer components

 

 

 

 

 

 

a)

Core (Kg)

 

 

 

 

 

 

b

Windings (Kg)

 

 

 

 

 

 


 

c)

Insulation (Kg)

 

 

 

 

 

 

d)

Tank and fittings (Kg)

 

 

 

 

 

 

e)

Oil (Kg)

 

 

 

 

 

 

f)

Untanking weight (heaviest piece) (Kg)

 

 

 

 

 

 

g)

Total weight Kg

 

 

 

 

 

 

h)

Weight of heaviest package KG

 

 

 

 

 

 

i)

Total shipping weight (Kg)

 

 

 

 

 

 

j)

Parts detached for transport

 

 

 

 

 

 

24

Permissible overload (% of rating & time in minutes)

 

 

 

 

 

 

25

Clearances

 

 

 

 

 

 

a)

Minimum clearance between phases

 

 

 

 

 

 

i)

In oil (mm)

 

 

 

 

 

 

ii)

In air (mm)

 

 

 

 

 

 

b)

Minimum clearance of HV winding to tank in oil (mm)

 

 

 

 

 

 

c)

Minimum clearance of HV winding of earth in oil (mm)

 

 

 

 

 

 

d)

Clearance between core (mm) and coil

 

 

 

 

 

 

e)

Clearance between coil (mm)

 

 

 

 

 

 

f)

Clearance between neutral to ground in air (mm)

 

 

 

 

 

 

26

Conservator

 

 

 

 

 

 

a)

Total volume (ltrs)

 

 

 

 

 

 

b)

Volume between highest and lowest levels (ltrs)

 

 

 

 

 

 

27

Capacitance values

 

 

 

 

 

 

a)

HV to earth (pf)

 

 

 

 

 

 


 

b)

LV to earth (pf)

 

 

 

 

 

 

28a)

Type of oil preservation

 

 

 

 

 

 

b)

Material of air cell

 

 

 

 

 

 

c)

Continuous temp. withstand capability of the air cell

 

 

 

 

 

 

29 a)

No.of pressure relief device provided

 

 

 

 

 

 

b)

Operation pressure of pressure relief device

 

 

 

 

 

 

30

Oil 

 

 

 

 

 

 

a)

Quality of oil

 

 

 

 

 

 

i)

Moisture content (ppm)

 

 

 

 

 

 

ii)

Max tan delta value (at 90 deg.C)

 

 

 

 

 

 

iii)

Resistivity (ohm – cm)

 

 

 

 

 

 

iv)

Breakdown strength (kv)

 

 

 

 

 

 

v)

Interfacial tension at 27 deg.C (min)

 

 

 

 

 

 

b)

Quantity including 10% extra (Ltrs)

 

 

 

 

 

 

c)

Standards applicable

 

 

 

 

 

 

31

Core 

 

 

 

 

 

 

a)

Type of construction

 

 

 

 

 

 

b)

Net core area (mm.sq)

 

 

 

 

 

 

c)

Core material and grade used

 

 

 

 

 

 

d)

Type of joint between core and yoke

 

 

 

 

 

 

e)

Thickness of stamping (mm)

 

 

 

 

 

 

f)

Percentage silicon content (%)

 

 

 

 

 

 

g)

Maximum flux density in core at rated frequency at

 

 

 

 

 

 


 

i)

90% voltage (wb/sq.m)

 

 

 

 

 

 

ii)

100% voltage (wb/sq.m)

 

 

 

 

 

 

iii)

110% voltage (wb/sq.m)

 

 

 

 

 

 

32

Winding

 

 

 

 

 

 

a)

Type of winding

 

 

 

 

 

 

b)

Current density at rated load

 

 

 

 

 

 

i)

HV (A/Sq.cm)

 

 

 

 

 

 

ii)

LV (A/Sq.cm)

 

 

 

 

 

 

iii)

Regulating winding (A/Sq.cm)

 

 

 

 

 

 

c)

Conductor area

 

 

 

 

 

 

 

i) HV (sq.mm)

 

 

 

 

 

 

 

ii) LV (sq.mm)

 

 

 

 

 

 

 

Iii) Regulating winding

 

 

 

 

 

 

d)

Maximum current density under short circuit

 

 

 

 

 

 

i)

i) HV (sq.mm)

 

 

 

 

 

 

 

ii) LV (sq.mm)

 

 

 

 

 

 

e)

Magnetising inrush current (Amps)

 

 

 

 

 

 

f)

No load current (Amps) at rated frequency and at

 

 

 

 

 

 

i)

90% voltage (wb/sq.m)

 

 

 

 

 

 

ii)

100% voltage (wb/sq.m)

 

 

 

 

 

 

iii)

110% voltage (wb/sq.m)

 

 

 

 

 

 

g)

Magnetising current at rated frequency and at rated voltage

 

 

 

 

 

 

33

Tank 

 

 

 

 

 

 

a)

Type

 

 

 

 

 

 


 

b)

Material 

 

 

 

 

 

 

c)

Approx Thickness of

 

 

 

 

 

 

i)

Sides (mm)

 

 

 

 

 

 

ii)

Bottom (mm)

 

 

 

 

 

 

iii)

Cover (mm)

 

 

 

 

 

 

34

Radiator 

 

 

 

 

 

 

a)

Make

 

 

 

 

 

 

b)

Material 

 

 

 

 

 

 

c)

Thickness 

 

 

 

 

 

 

35

Vacuum withstand capability of

 

 

 

 

 

 

a)

Main tank (torr)

 

 

 

 

 

 

b)

Radiators accessories (torr)

 

 

 

 

 

 

36

Pressure withstanding capability of

 

 

 

 

 

 

a)

Main Tank

 

 

 

 

 

 

b)

Radiator  and accessories

 

 

 

 

 

 

37

Temperature indicators

 

 

 

 

 

 

a)

OTI

 

 

 

 

 

 

i)

Manufacturer

 

 

 

 

 

 

ii)

Range

 

 

 

 

 

 

iii)

Accuracy

 

 

 

 

 

 

b)

WTI

 

 

 

 

 

 

i)

Manufacturer

 

 

 

 

 

 

ii)

Range

 

 

 

 

 

 

iii)

Accuracy

 

 

 

 

 

 


 

c)

RWTI

 

 

 

 

 

 

i)

Manufacturer

 

 

 

 

 

 

ii)

Range

 

 

 

 

 

 

iii)

Accuracy

 

 

 

 

 

 

iv)

Auxiliary supply used

 

 

 

 

 

 

38

Terminal connectors

 

 

 

 

 

 

a)

Make

 

 

 

 

 

 

b)

Whether type tested

 

 

 

 

 

 

c)

Governing standard

 

 

Note: If there is any change in the above GTPs, same shall conform  to Technical Specifications/relevant ISS. If there is any change in GTPs, so warranted by specific make of equipment, same shall be taken care at the time of approval of drawings.